Land surface is worn away by the action of wind water and gravity
erosion
the settling out of soil particles transported by water and wind
Sedementation
water erosion can be classified as --- erosion, --- or ---
overland, stream, channel
four processes of overland erosion
rain, sheet, rill, gully
four principle factors influencing soil erosion
soil, vegetative, climate, topography
apply --- practices to protect the disturbed area from off-site runoff and to protect off-site
areas from sediment damage
perimeter control
apply _____ practices to prevent excessive on site damage
erosion control
Keep runoff velocities ___ and _____ runoff on the site.
, low and retain
stabilize disturbed areas ____ after final grading to prevent erosion
immediately
Implement a thorough _____ and _____ (inspection) program as required in the
Construction Generic Permit (CGP)
maintenance and follow up
soil particles smaller than 0.002mm are classified as ___ and ___
clay and muck
soil types that cause the most erosion/turbidity problems
clay and muck
Type A soils have ___ infiltration rates and ___ runoff potential when wetted
high, low
Type D soils have ___ infiltration rates and ___ runoff potential when wetted
low, high
(these are mucks and clays)
The only factor in the universal soil equation loss equation that is beyond the developers
control
Rainfall
_____, _____, and _____ are the factors most easily manipulated by the developer
Control Inspector Cert Exam Questions and
Answers
Land surface is worn away by the action of wind water and gravity
erosion
the settling out of soil particles transported by water and wind
Sedementation
water erosion can be classified as --- erosion, --- or ---
overland, stream, channel
four processes of overland erosion
rain, sheet, rill, gully
four principle factors influencing soil erosion
soil, vegetative, climate, topography
apply --- practices to protect the disturbed area from off-site runoff and to protect off-site
areas from sediment damage
perimeter control
apply _____ practices to prevent excessive on site damage
erosion control
Keep runoff velocities ___ and _____ runoff on the site.
, low and retain
stabilize disturbed areas ____ after final grading to prevent erosion
immediately
Implement a thorough _____ and _____ (inspection) program as required in the
Construction Generic Permit (CGP)
maintenance and follow up
soil particles smaller than 0.002mm are classified as ___ and ___
clay and muck
soil types that cause the most erosion/turbidity problems
clay and muck
Type A soils have ___ infiltration rates and ___ runoff potential when wetted
high, low
Type D soils have ___ infiltration rates and ___ runoff potential when wetted
low, high
(these are mucks and clays)
The only factor in the universal soil equation loss equation that is beyond the developers
control
Rainfall
_____, _____, and _____ are the factors most easily manipulated by the developer