QUESTIONS AND CORRECT ANSWERS
Which approach to lessons learned helps identify most of the lessons learned on a project?
scheduling lessons learned regularly anonymous method for sumbitting without
managers present reminding them to be positive - Correct answers✔scheduling
lessons learned regularly
You are using earned value analysis to track your project's progress. In your project, earned value
is higher than planned value and actual value. That means the project is _____ schedule and
_____ budget. behind; under ahead of; under ahead of; over behind; over - Correct
answers✔ahead of; under
The people assigned to your project have high billable rates, and the project budget doesn't
provide much of a buffer over your estimated total project cost. Fortunately, the project
finish date has some wiggle room. Which measure of progress is most important to track in
this situation? actual work remaining duration actual start date actual duration - Correct
answers✔
You are fortunate to have an experienced team that has worked together for more than a year and
is familiar with the project work. What would you expect as your main activity managing this
team?
remove obstacles clearly describe the work
provide feedback resolve problems quickly -
Correct answers✔remo