What does this permit regulate? - ANSWER Discharges of pollutants in storm water
associated with construction activity (storm water discharges) to waters of the united states
from construction site that disturb one or more acres of land surface, or that are part of a
common plan of development or sale that disturbs more than one acre of land surface.
The person in charge of the utility company, municipality, or other public or private company
or agency that owns or operates the __________ may also serve as the LRP. -
ANSWER LUP
Sediment basins, at a minimum, shall be designed according to the CASQA Construction
BMP Guidance Handbook. - ANSWER True
In the RUSLE equation, "P" stands for - ANSWER Management operations and support
practices.
Management operations and support practices. - ANSWER Management operations
and support practices.
When does risk level one has to sample? - ANSWER When required for non-visible
pollutants.
ATS instruments shall record which of the following? - ANSWER Flow, turbidity, and pH
Which factor(s) of RUSLE can be based on site-specific analysis rather than maps? -
ANSWER K and LS
, Failure to obtain coverage under the permit for storm water discharges to waters of the US is
a violation of the - ANSWER Clean Water Act and California Water Code
For traditional construction projects the LRP may be - ANSWER The person who
possesses real properly interest in the land upon which the construction activities will occur
for the regulated site
What does NTU measure? - ANSWER a measurement of optical properties of a liquid
that cause light rays to be scattered and absorbed rather than transmitted in straight lines
through a sample.
Inspection Records have to be kept until the project is complete or three years, whichever
comes first. - ANSWER False
Which factor(s) of RUSLE must be changed to recalculate risk when the construction
duration has changed? - ANSWER R
BMP stands for - ANSWER Best Management Practice
Do type 1 LUPs typically have a high potential to impact storm quality? - ANSWER No
What does RUSLE stand for? - ANSWER Revised Universal Soil Loss Equation
A discharger must notify the Regional Water Boards if there are planned changes in the
construction activity that - ANSWER May result in non-compliance
A qualifying storm event is - ANSWER A rain even that produces 1/2 inch or more of
precipitation with a period of 48 hours or more between rain events.