FDNYC F60 Fireguard Test EXAM
Questions and Answers (Verified
Answers) (Latest Update 2025) UPDATE!!
F60 Fireguard test
For hot work operation with citywide permit, the owner of the premises of the
hot work operation areas must be notified in writing by the citywide permit
holder ______ the hot work is to be started. - (ANSWER)at least 48 hours before
The pre-hot work check must be conducted by the responsible person before hot
work is authorized and __________ - (ANSWER)least once per day.
The check reports must be kept at the work site during the work, made available
for inspection by a representative of the FDNY, and maintained on the premises
for a minimum of - (ANSWER)48 hours after work is complete.
A pre-hot work check must be conducted at least - (ANSWER)once per day
Hot work operations involving cutting or welding shall be conducted at least -
(ANSWER)35 feet from combustible materials and combustible waste
All other hot work operations shall be conducted at least - (ANSWER)25 feet from
combustible materials and combustible waste