Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CIT 492 FINAL EXAM QUESTIONS AND ANSWER WITH VERIFIED SOLUTIONS GRADED A+ TESTED AND APPROVED 2025/2026 LATEST

Beoordeling
-
Verkocht
-
Pagina's
34
Cijfer
A+
Geüpload op
29-09-2025
Geschreven in
2025/2026

CIT 492 FINAL EXAM QUESTIONS AND ANSWER WITH VERIFIED SOLUTIONS GRADED A+ TESTED AND APPROVED 2025/2026 LATEST

Instelling
Vak

Voorbeeld van de inhoud

CIT 492 FINAL EXAM QUESTIONS AND ANSWER
WITH VERIFIED SOLUTIONS GRADED A+ TESTED
AND APPROVED 2025/2026 LATEST



What is the late start time for Activity E given the activity times and
precedence requirements shown in the table?

ActivityTimePredecessorA5--B7--C8AD7AE4BF8C, DG9E, FH7G --
ANSWER--17



It costs $75 per day for each day that a construction crew is on site.
The project manager determines that most activities can be crashed
and has listed the crashing costs next to the minimum time for each
activity. Use this information to determine the lowest cost for this
project. All times given are in days.ActivityNormal TimeMinimum
TimeCrash Cost ($/day)PredecessorA106$70--B63$40--C22--
BD42$60CE64$80AF85$90D, E --ANSWER--$1,780



Use the network diagram and activity lengths in the nodes to
determine the early finish time for activity G. --ANSWER--26



Use the Gantt chart and activity list to determine when resource 3 is
free.

Page 1 of 34

,ActivityResourcesActivityResourcesR3M1H1K5G4J3F2P1B2S2T4
W3 --ANSWER--Between 10 and 20



Use the Gantt chart and activity list to determine which resource has
the greatest continual use.

ActivityResourcesActivityResourcesR5M1H1K5G5J3F2P1B2S2T4
W3 --ANSWER--Resource 5



Use the information in the table to determine the late finish time for
Activity B.

TaskPredecessorDurationEarly StartEarly FinishLate StartLate
FinishA--8BA14CA238DC, B62326EC32FD, E3238 --ANSWER--
Day 26



Hammock activities allow: --ANSWER--The project team to better
disaggregate the overall project network into logical summaries.



An activity has an optimistic time estimate of 17 days, a most likely
estimate of 22 days, and a pessimistic estimate of 32 days. What is the
expected duration of the activity? --ANSWER--22.83 Days




Page 2 of 34

,Which technique would accelerate the completion of a project? --
ANSWER--Laddering



Summaries for some subsets of the activities identified in the overall
project network are called: --ANSWER--Hammock Activities



The BEST approach to network representation of a large and hugely
complex project is to --ANSWER--Simplify network logic and reduce
it to the most meaningful relationships.



Use the Gantt chart and the activity list to determine when resource 5
is free.

ActivityResourcesActivityResourcesA1F1B5G2C4H5D3J3E2K4 --
ANSWER--Between 45 and 60



The AOA network described by this table needs:

ActivityPredecessorA--B--CA, BDBEC, D --ANSWER--One dummy
activity.



Use the network diagram and activity lengths in the nodes to
determine the late finish time for activity C. --ANSWER--14


Page 3 of 34

, The process of accelerating a project is referred to as: --ANSWER--
Crashing



Activities C, D, and E in the project represented by the network are to
be hammocked. What are the early start and late finish times of the
hammock activity? --ANSWER--6, 26



A project has the precedence requirements and activity durations
shown in the table. After he draws the network, the project manager
decides that activities H and I can be represented by a hammock
activity. What are the early start and late finish times associated with
this hammock activity?TimePredecessorA7
B8AC13BD8CE7AF6EG6AH11GI12HJ14D, F, I --ANSWER--13,
36



Use the network diagram and activity lengths in the nodes to
determine the early start time for activity D. --ANSWER--14



In general, the better candidates for shortening are: --ANSWER--
Early tasks opposed to later tasks.



Page 4 of 34

Geschreven voor

Vak

Documentinformatie

Geüpload op
29 september 2025
Aantal pagina's
34
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$26.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
TESTBANKNURSEHUB
4.0
(2)

Maak kennis met de verkoper

Seller avatar
TESTBANKNURSEHUB Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
8
Lid sinds
8 maanden
Aantal volgers
0
Documenten
3097
Laatst verkocht
2 weken geleden
your document plug

I offer all types of documents notes, exams and study guide practice exams. Feel free to contact me for any clarification and document prices.

4.0

2 beoordelingen

5
0
4
2
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen