What is the late start time for Activity E given the activity times and
precedence requirements shown in the table?
ActivityTimePredecessorA5--B7--C8AD7AE4BF8C, DG9E, FH7G --
ANSWER--17
It costs $75 per day for each day that a construction crew is on site.
The project manager determines that most activities can be crashed
and has listed the crashing costs next to the minimum time for each
activity. Use this information to determine the lowest cost for this
project. All times given are in days.ActivityNormal TimeMinimum
TimeCrash Cost ($/day)PredecessorA106$70--B63$40--C22--
BD42$60CE64$80AF85$90D, E --ANSWER--$1,780
Use the network diagram and activity lengths in the nodes to
determine the early finish time for activity G. --ANSWER--26
Use the Gantt chart and activity list to determine when resource 3 is
free.
Page 1 of 34
,ActivityResourcesActivityResourcesR3M1H1K5G4J3F2P1B2S2T4
W3 --ANSWER--Between 10 and 20
Use the Gantt chart and activity list to determine which resource has
the greatest continual use.
ActivityResourcesActivityResourcesR5M1H1K5G5J3F2P1B2S2T4
W3 --ANSWER--Resource 5
Use the information in the table to determine the late finish time for
Activity B.
TaskPredecessorDurationEarly StartEarly FinishLate StartLate
FinishA--8BA14CA238DC, B62326EC32FD, E3238 --ANSWER--
Day 26
Hammock activities allow: --ANSWER--The project team to better
disaggregate the overall project network into logical summaries.
An activity has an optimistic time estimate of 17 days, a most likely
estimate of 22 days, and a pessimistic estimate of 32 days. What is the
expected duration of the activity? --ANSWER--22.83 Days
Page 2 of 34
,Which technique would accelerate the completion of a project? --
ANSWER--Laddering
Summaries for some subsets of the activities identified in the overall
project network are called: --ANSWER--Hammock Activities
The BEST approach to network representation of a large and hugely
complex project is to --ANSWER--Simplify network logic and reduce
it to the most meaningful relationships.
Use the Gantt chart and the activity list to determine when resource 5
is free.
ActivityResourcesActivityResourcesA1F1B5G2C4H5D3J3E2K4 --
ANSWER--Between 45 and 60
The AOA network described by this table needs:
ActivityPredecessorA--B--CA, BDBEC, D --ANSWER--One dummy
activity.
Use the network diagram and activity lengths in the nodes to
determine the late finish time for activity C. --ANSWER--14
Page 3 of 34
, The process of accelerating a project is referred to as: --ANSWER--
Crashing
Activities C, D, and E in the project represented by the network are to
be hammocked. What are the early start and late finish times of the
hammock activity? --ANSWER--6, 26
A project has the precedence requirements and activity durations
shown in the table. After he draws the network, the project manager
decides that activities H and I can be represented by a hammock
activity. What are the early start and late finish times associated with
this hammock activity?TimePredecessorA7
B8AC13BD8CE7AF6EG6AH11GI12HJ14D, F, I --ANSWER--13,
36
Use the network diagram and activity lengths in the nodes to
determine the early start time for activity D. --ANSWER--14
In general, the better candidates for shortening are: --ANSWER--
Early tasks opposed to later tasks.