PMT 0170 RISK MANAGEMENT EXAM
2025/2026 QUESTIONS AND ANSWERS
100% PASS
Why are Monte Carlo simulations used in program schedule analysis? 10.2 - ANS To find the
cumulative effect of multiple risks on total project schedule duration or total project cost
A shortage of steel has caused a delay in one of the tasks until the material is available. The
original plan estimated the material to be available in 6 weeks, but the shortage continues.
What would be an appropriate step in tracking and managing this issue? 15.3 - ANS Adjust
the corrective action plan and issue level as warranted.
Since risks should be closely tied to individual tasks and deliverables, which of the following
should be used as a cross-reference to each risk? 31.1 - ANS Work Breakdown Structure
(WBS) number
The following describes which type of category of risk: Two legacy software systems must be
combined into one system in order to operate a new piece of hardware. Programmers must
find a way to ensure that old data records in each system are still editable. If not, the hardware
will not operate correctly. 7.2 - ANS Technical
Which of the following is important for good government/contractor coordination of risk
management (RM)? (Select two that apply.) 6.3 - ANS Not:
Common approaches to addressing risk.
All personnel committing to plan and execute a successful risk management (RM) program
1 @COPYRIGHT 2025/2026 ALLRIGHTS RESERVED
2025/2026 QUESTIONS AND ANSWERS
100% PASS
Why are Monte Carlo simulations used in program schedule analysis? 10.2 - ANS To find the
cumulative effect of multiple risks on total project schedule duration or total project cost
A shortage of steel has caused a delay in one of the tasks until the material is available. The
original plan estimated the material to be available in 6 weeks, but the shortage continues.
What would be an appropriate step in tracking and managing this issue? 15.3 - ANS Adjust
the corrective action plan and issue level as warranted.
Since risks should be closely tied to individual tasks and deliverables, which of the following
should be used as a cross-reference to each risk? 31.1 - ANS Work Breakdown Structure
(WBS) number
The following describes which type of category of risk: Two legacy software systems must be
combined into one system in order to operate a new piece of hardware. Programmers must
find a way to ensure that old data records in each system are still editable. If not, the hardware
will not operate correctly. 7.2 - ANS Technical
Which of the following is important for good government/contractor coordination of risk
management (RM)? (Select two that apply.) 6.3 - ANS Not:
Common approaches to addressing risk.
All personnel committing to plan and execute a successful risk management (RM) program