1. Materials in a Plant 2001 SSA are ___________ funded. - Correct answer-b.
AWCF
2. The ERP structure in GCSS-Army uses combinations of organizational elements
to represent SSAs and Units. The ____________ is a designated virtual area within
each plant where planning occurs for an activity. - Correct answer-b. MRP area
3. The physical slot where material resides in Plant 2001 is known as the
_________. - Correct answer-d. Bin
4. The Advance Shipment Notification (ASN) triggers the creation of a (an)
____________. - Correct answer-b. inbound delivery
5. Which source and destination listed below represents a goods receipt going to
the warehouse for putaway? - Correct answer-c. 902 500000XXXX to RAK
WACBA
6. Data from transportation or supply discrepancies is automatically transferred to
WEBSDR. - Correct answer-b. False