According to A201, the contract documents consist of the agreement between: - Answers
contractor & owner
What portion of the contract documents consist of the written requirements for materials,
equipment, construction systems, standards and workmanship for the work, and performance
of related services? - Answers specifications
According to A201, who is deemed the owner of the contract documents? - Answers architect
According to A201, the ___________ is responsible for securing and paying for all necessary
easements on a construction project. - Answers owner
According to A201, the owner is not responsible for which of the following: - Answers permits
and fees
The _________ shall furnish surveys describing physical characteristics, legal limitations and
utility locations for the site of the project and a legal description of the site. - Answers owner
If a contractor fails to correct any deficiency within a __________ period after receipt of notice,
the owner without prejudice to other remedies may correct such deficiencies. - Answers 10 day
According to A201, the __________ shall take field measurements of any present conditions
connected to that portion of the work and notice any conditions at the site affecting it. -
Answers contractor
A contractor recognized there was a mistake in the contract documents regarding a
construction activity an did not report it to the architect. The contractor performed the work
anyway, knowing there was a mistake. Who shall bear the costs for correcting this mistake> -
Answers the contractor
The ___________ shall be exclusively accountable for and have control over construction means,
methods, techniques, sequences and procedures, and for coordinating all portions of the work
under the contract. - Answers contractor
According to A201, the __________ shall secure and pay all necessary inspections for proper
execution and completion of the work which are customarily secured after execution of the
contract documents. - Answers contractor
According to A201, unless otherwise stated, the _________ is responsible for securing and paying
the permit fees. - Answers contractor
A contractor encounters conditions at the jobsite which differ extensively from those indicated
in the contact documents.
, The contractor shall immediately report such conditions and in no event later than
______________ days after observation of the conditions. - Answers 14
A contractor observed that a vent pipe that was supposed to be located in a concealed space
was actually falling in a doorway. According A201, the contractor must notify the architect of
the discrepancy within: - Answers 14 days
If, in the course of the work, the Contractor encounters human remains or recognizes the
existence of burial markers, the Contractor shall suspend operations ____________ and notify the
Owner and Architect. - Answers immediately
According to A201, which of the following allowances shall be included in the contract sum but
not in the allowances? - Answers contractor's cost for unloading at the site
According to A201, which of the following shall be included in the contract documents as
allowances? - Answers taxes
After being awarded the contract, the contractor shall prepare and submit for the owner's and
architect's information a contractor's __________ for the work. - Answers construction schedule
A contractor shall submit a construction schedule: - Answers immediately after being awarded
the contract
According to A201, the contractor shall maintain at the site for the owner ____________ record
copy(s) of the drawings and specifications. - Answers 1
How many copies of a change order shall the contractor keep at the job site during construction?
- Answers one copy
According to A201, drawings, diagrams, schedules and other data specially prepared for the
work by the contractor to illustrate some portion of the project are known as - Answers shop
drawings
According to AIA documents, shop drawing, product data, and samples are: - Answers not
contract documents
Shop drawings submitted by contractor and approved by architect: - Answers will not relieve the
contractor from responsibility for errors or omissions in the drawings
The ___________ shall be responsible for keeping the project area free from accumulation of
waste materials or rubbish caused by operations under the contract. - Answers contractor
A contractor has reason to believe that the contract documents contain a particular design that
is a trademark infringement and does not inform the architect of such infringement. According
to A201, who is responsible for any loss or lawsuits if the design develops into a trademark
infringement? - Answers the contractor