An employer is not required to keep written health records
for:
a. 10 employees or less
b. 20 employees or less
c. 30 employees or less
d. When the business is family operated - ANSWERS-A ...
Explanation: 10 employees or less.
The specification referring to a standard established for
either a material, a test method, or an insulation procedure
is called a ________.
a. Reference
b. Performance
c. Descriptive
,d. Propriety - ANSWERS-A ... Explanation: A reference.
Which of these is classified as a job-related direct cost?
a. Trade Association membership
b. Contractor's license fee
c. Performance bond
d. Office rent - ANSWERS-C ... Explanation: A performance
bond is considered to be a job-related direct cost.
If a contract is made between a contractor and an
unlicensed person who is in violation of the law?
a. The contractor
b. Both the contractor and the unlicensed person
c. The unlicensed person
d. Only the unlicensed person if he didn't notify the
contractor - ANSWERS-B ... Explanation: Both parties
involved are in violation of the law.
Under the terms found in a typical construction project, the
contractor is usually to held to guarantee that the
completed project:
a. Is free of defects and design
,b. Will accomplish the intended purpose
c. Is guaranteed a certain amount of time
d. Has been executed with the quality of workmanship and
materials specified in the contract documents - ANSWERS-D
... Explanation: The completed project has been executed
with the quality of workmanship and materials specified in
the contract documents.
If a subcontractor signs an unconditional waiver and
release, this would imply that a:
a. Subcontractor cannot ask anything more of the owner
b. Owner cannot ask anything more of the subcontractor
c. Subcontractor cannot get anything from the prime
d. Subcontractor cannot ask anything more of the prime -
ANSWERS-A ... Explanation: Once the subcontractor signs an
unconditional waiver and release, the subcontractor cannot
ask anything more of the owner.
Any applicant who has been denied a license to practice on
the basis of credentials, or failure to pass a required
examination, may submit a request for agency review to the
executive director ____ following notification of the denial
of a license or refusal to renew or reinstate a license.
a. Within 10 days
, b. Within 20 days
c. Within 30 days
d. Within 60 days - ANSWERS-5. C ... Explanation: Any
applicant who has been denied a license to practice on the
basis of credentials, character, or failure to pass a required
examination, or who has been refused renewal or
reinstatement of a license to practice on the basis that the
applicant does not meet qualifications for continued
licensure in any occupation or profession under the
jurisdiction of the division may submit a request for agency
review to the executive director within 30 days following
notification of the denial of a license or refusal to renew or
reinstate a license.
What should a contractor do if after starting a home
improvement project the contractor discovers that the
details and specifications do NOT correctly show the existing
construction?
a. Stop and work on a correction
b. Stop the job and inform the owner or his agent
c. Continue the work if variations are only minor
d. Stop the job and inform the Building Department -
ANSWERS-B ... Explanation: Any details and specifications
are not represented correctly then it is the contractor's duty
to inform the owner or his agent.