On a piece of scratch paper, draw the network associated with this table and determine the following.
What is the critical path? - CORRECT ANSWERS-
On a piece of scratch paper, draw the network above to determine the following. What is the duration of
the critical path? - CORRECT ANSWERS-
A SWOT analysis provides the Project Manager with
a. a direct linkage to goals and an identifiable strategic alternative.
b. an identifiable strategic alternative.
c. potential critical issues facing the organization.
d. an identifiable strategic alternative and potential critical issues facing the organization.
e. a direct linkage to goals. - CORRECT ANSWERS-d. an identifiable strategic alternative and potential
critical issues facing the organization.
In a SWOT analysis, strong competition, reduced product demand, and a maturing product life cycle are
examples of external __________.
a. weaknesses
b. targets
c. opportunities
d. strengths
e. threats - CORRECT ANSWERS-e. threats
A project life cycle
,a. must be dogmatically followed.
b. will always have a phase called 'visioning'.
c. reduces the amount of planning necessary.
d. can vary based on the industry.
e. will only ever consist of four phases. - CORRECT ANSWERS-d. can vary based on the industry.
Which of these is NOT part of the "sociocultural dimension" of project management?
a. Managing customer expectations
b. Leadership
c. Resource allocation
d. Dealing with politics
e. Negotiation - CORRECT ANSWERS-c. Resource allocation
Any project life cycle is made up of stages. The project's schedule and budget will be determined in the
___________ stage of the project life cycle.
a. planning
b. defining
c. executing
d. closing
e. conceptual - CORRECT ANSWERS-a. planning
Training the customer, releasing staff and resources occurs in the ________ stage of project life cycle.
a. defining
b. planning
c. conceptual
d. closing
,e. executing - CORRECT ANSWERS-d. closing
A series of coordinated, related, multiple projects that continue over an extended time period and are
intended to achieve a goal is known as a
a. Campaign.
b. Strategy.
c. Venture.
d. Program.
e. Crusade. - CORRECT ANSWERS-d. program
An increase in the complexity of projects, because projects typically include the latest advances, can be
the result of a growth in new __________.
a. services
b. products and services
c. products
d. processes
e. knowledge - CORRECT ANSWERS-e. knowledge
Which of the following is NOT true about project management?
a. It is not limited to the private sector.
b. Many opportunities are available for individuals interested in this career path.
c. It focuses primarily on technical processes.
d. It is a set of tools.
e. It improves one's ability to plan, implement and manage activities to accomplish specific
organizational objectives - CORRECT ANSWERS-c. It focuses primarily on technical processes
In which stage of the project life cycle is the project's schedule and budget determined?
, a. Closing
b. Identifying
c. Planning
d. Defining
e. Executing - CORRECT ANSWERS-c. planning
A project does not include
a. repetitive, same or similar work.
b. unique elements.
c. creating a new product or service.
d. a specific objective.
e. developing a new process. - CORRECT ANSWERS-a. repetitive, same or similar work
Project management is ideally suited for a business environment requiring all of the following EXCEPT
a. Repeatability.
b. Accountability.
c. Innovation.
d. Flexibility.
e. Speed. - CORRECT ANSWERS-a. repeatability
Which of the choices listed below is NOT considered to be a characteristic of a project?
a. For internal use only
b. An established objective
c. Specific time, cost and performance requirements
d. A clear beginning and end