When testing the #2 check valve of a double check valve
assembly you open #4 testcock and the water recedes
from the sight tube.
This indicates the following:
a) The #2 shut off valve is leaking
b) The #2 check valve is leaking
c) The #2 shut off valve is leaking with demand
d) The #1 check valve is leaking - ANSWER-c) The #2
shut off valve is leaking with demand
,When testing the #2 check valve of a reduced pressure
principle backflow prevention assembly you apply
pressure to the low side of the #2 check valve and the
indicator on your test kit drops to the relief valve opening
point with water discharging from the relief valve. How do
you proceed?
a) Open the #2 shut off valve to compensate for a leaking
#1 shut off valve
b) Open the high side bleed needle valve to compensate
for a leaking check valve
c) Close the #4 testcock to compensate for a leaking #1
shut off valve
d) Open the low side bleed needle valve - ANSWER-d)
Open the low side bleed needle valve
, When testing the check valve of a spill resistant vacuum
breaker you are attempting to lower the pressure in the
valve body. As you attempt to lower the pressure water
continues to discharge from the assembly with no
decrease in pressure. What does this indicate?
a) The vent screw is not removed
b) The check valve is leaking
c) The #2 shut off valve is leaking
d) The #1 shut off valve is leaking - ANSWER-d) The #1
shut off valve is leaking
When testing the inlet of a pressure vacuum breaker you
have opened the high side bleed needle valve on quarter