Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CMGT 3500 TEST 3 2025 EXAM QUESTIONS AND ANSWERS

Beoordeling
-
Verkocht
-
Pagina's
3
Cijfer
A+
Geüpload op
17-10-2025
Geschreven in
2025/2026

CMGT 3500 TEST 3 2025 EXAM QUESTIONS AND ANSWERS Unlike other businesses, the construction industry is paid on periodic payments for progress of completion of a project. - ANSWER-True An express warranty is one that clearly stated either verbally in writing. - ANSWER-True The duration of a project is measured against substantial completion to determine: - ANSWER-When the last periodic payment can be made Retainage is: - ANSWER-Used as incentive for the contractor to complete the project Project Closeout - ANSWER-- Preparations should begin at the start of construction - Should include Contractor self-inspections - May create a loss on a project to the contractor if it is drawn out -Provides the creation of a punchlist A warranty is - ANSWER-A certification that an aspect of a contract is promised to be, and based on a specified time period of validity When a project is accepted, the Owner should carefully inspect the project for any defects, and resolution of defects should take place after final payment is made. - ANSWER-False Patent defects are defects not readily observed - ANSWER-False The general contractor is responsible for: - ANSWER--Performance of subcontractors -All materials and equipment furnished -Contractor assisted selection of materials with the owner An implied warranty means that the contractor guarantees that the completed project will be suitable for its intended purpose. - ANSWER-False The courts have ruled that Owner's inspection and acceptance of work waive any claims that result from the Contractor's defective performance, except latent defects. - ANSWER-True Subcontractors: - ANSWER-Are independent contractors hired by General Contractors General Contractors: - ANSWER-Have the right to "take steps it deems necessary to correct deficiencies and charge the cost..." against subcontractors

Meer zien Lees minder
Instelling
CMGT 3500 3 2025
Vak
CMGT 3500 3 2025

Voorbeeld van de inhoud

CMGT 3500 TEST 3 2025 EXAM
QUESTIONS AND ANSWERS
Unlike other businesses, the construction industry is paid on periodic payments for
progress of completion of a project. - ANSWER-True

An express warranty is one that clearly stated either verbally in writing. - ANSWER-
True

The duration of a project is measured against substantial completion to determine: -
ANSWER-When the last periodic payment can be made

Retainage is: - ANSWER-Used as incentive for the contractor to complete the project

Project Closeout - ANSWER-- Preparations should begin at the start of construction
- Should include Contractor self-inspections
- May create a loss on a project to the contractor if it is drawn out
-Provides the creation of a punchlist

A warranty is - ANSWER-A certification that an aspect of a contract is promised to
be, and based on a specified time period of validity

When a project is accepted, the Owner should carefully inspect the project for any
defects, and resolution of defects should take place after final payment is made. -
ANSWER-False

Patent defects are defects not readily observed - ANSWER-False

The general contractor is responsible for: - ANSWER--Performance of
subcontractors
-All materials and equipment furnished
-Contractor assisted selection of materials with the owner

An implied warranty means that the contractor guarantees that the completed project
will be suitable for its intended purpose. - ANSWER-False

The courts have ruled that Owner's inspection and acceptance of work waive any
claims that result from the Contractor's defective performance, except latent defects.
- ANSWER-True

Subcontractors: - ANSWER-Are independent contractors hired by General
Contractors

General Contractors: - ANSWER-Have the right to "take steps it deems necessary to
correct deficiencies and charge the cost..." against subcontractors

Geschreven voor

Instelling
CMGT 3500 3 2025
Vak
CMGT 3500 3 2025

Documentinformatie

Geüpload op
17 oktober 2025
Aantal pagina's
3
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$15.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Freshy Oxford University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
61
Lid sinds
2 jaar
Aantal volgers
4
Documenten
6990
Laatst verkocht
2 weken geleden

3.6

10 beoordelingen

5
3
4
4
3
1
2
0
1
2

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen