Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CMGT 3500 TEST 3 2025 EXAM QUESTIONS AND ANSWERS

Beoordeling
-
Verkocht
-
Pagina's
6
Cijfer
A+
Geüpload op
17-10-2025
Geschreven in
2025/2026

CMGT 3500 TEST 3 2025 EXAM QUESTIONS AND ANSWERS Change - ANSWER-Also referred to as extras. When owner makes them they become modification of contract. If this impacts project cost/duration a change order is required Change Order - ANSWER-Changes issued by the owner that requires a change to the original contract. When GC receives modification proposal- must evaluate the potential impact the changes will have on the cost/duration, subcontractors involved in change must also submit quotations. If quotation is acceptable, GC will submit a change order. Owner evaluates prices proposed by GC, then issues a formal change order to GC at agreed price, or on a cost-plus basis, or decides not to issue a change order. Field Change - ANSWER-Type of change that has no impact on the contract's duration or amount. Authorized by personnel in the field without owner approval. Typically, minor, but are required to facilitate the construction effort. Cardinal Change - ANSWER-a change order that is of such magnitude that the original scope of the project is altered to an extent that constitutes a new contract the owner, and the architect/engineer if the owner has transferred to them the ability to take on that responsibility - ANSWER-Who has the authority to make a change order? Pre-bid site investigation - ANSWER-Generally, includes information in the form of boring logs and results of tests on the indigenous soils, although may be an accurate representation of the site, it is common practice to stipulate that the contractor make an independent site visit and investigation. Differing Site Conditions - ANSWER-2 broad categories- the actual conditions differ materially or at variance with the conditions indicated in the contract documents. And the actual conditions are of an unusual nature and differ materially or are at variance with what the contractor should have reasonably anticipated- not foreseeable. Documentation - ANSWER-When dealing with changed conditions always use__________. Including photos, labor costs, equipment costs, etc. Whatever the contract states. Traditionally, contractor owns the float but the contract will state exactly. - ANSWER-Who owns float? Construction Schedules - ANSWER-Show the proposed sequence of work within the number of working days set up in the contract. Often the owner may require that this schedule be submitted before the pre-construction conference. The specific treatment of the schedule in the contract must be carefully examined to determine the impact of changes and delays. Different contractual methods to determine the duration of the project - ANSWER-Working day, fixed completion date, calendar days, and completion date

Meer zien Lees minder
Instelling
CMGT 3500 3 2025
Vak
CMGT 3500 3 2025

Voorbeeld van de inhoud

CMGT 3500 TEST 3 2025 EXAM
QUESTIONS AND ANSWERS
Change - ANSWER-Also referred to as extras. When owner makes them they
become modification of contract. If this impacts project cost/duration a change order
is required

Change Order - ANSWER-Changes issued by the owner that requires a change to
the original contract. When GC receives modification proposal- must evaluate the
potential impact the changes will have on the cost/duration, subcontractors involved
in change must also submit quotations. If quotation is acceptable, GC will submit a
change order. Owner evaluates prices proposed by GC, then issues a formal change
order to GC at agreed price, or on a cost-plus basis, or decides not to issue a
change order.

Field Change - ANSWER-Type of change that has no impact on the contract's
duration or amount. Authorized by personnel in the field without owner approval.
Typically, minor, but are required to facilitate the construction effort.

Cardinal Change - ANSWER-a change order that is of such magnitude that the
original scope of the project is altered to an extent that constitutes a new contract

the owner, and the architect/engineer if the owner has transferred to them the ability
to take on that responsibility - ANSWER-Who has the authority to make a change
order?

Pre-bid site investigation - ANSWER-Generally, includes information in the form of
boring logs and results of tests on the indigenous soils, although may be an accurate
representation of the site, it is common practice to stipulate that the contractor make
an independent site visit and investigation.

Differing Site Conditions - ANSWER-2 broad categories- the actual conditions differ
materially or at variance with the conditions indicated in the contract documents. And
the actual conditions are of an unusual nature and differ materially or are at variance
with what the contractor should have reasonably anticipated- not foreseeable.

Documentation - ANSWER-When dealing with changed conditions always
use__________. Including photos, labor costs, equipment costs, etc.

Whatever the contract states. Traditionally, contractor owns the float but the contract
will state exactly. - ANSWER-Who owns float?

Construction Schedules - ANSWER-Show the proposed sequence of work within the
number of working days set up in the contract. Often the owner may require that this
schedule be submitted before the pre-construction conference. The specific
treatment of the schedule in the contract must be carefully examined to determine
the impact of changes and delays.

, Different contractual methods to determine the duration of the project - ANSWER-
Working day, fixed completion date, calendar days, and completion date

Working day contractual method - ANSWER-any day except sat, sun, and holidays
in which the contractor performs work or could have performed work. most
appropriate when the site conditions are subject to delays caused by weather,
differing site conditions. Typically extended construction durations for severe
weather delays

Fixed completion date contractual method - ANSWER-Specified completion date
when the owner needs the project completed by

Calendar days contractual method - ANSWER-represents every day that takes
place, including weekends and holidays. Preferred when time extensions (from
adverse weather) are not generally anticipated

Completion date contractual method - ANSWER-owner would like to occupy and
utilize completed facility by a certain point in time, does not establish a clear value of
the project duration. Sets the completion date for the project, but not the starting
date.

Liquidated damages - ANSWER-The cost to the contractor for each day that the
project extends beyond the contract time. If the project is stated at being 180 days,
the contract may state the contractor must pay $1000 for each day beyond the 180.
These damages provide compensation to the owner for financial and other losses
resulting from delayed completion

3 types of delays - ANSWER-caused by the contractor or the contractors agents,
caused by the owner or the owners agents, caused by acts of god.

Excusable delays (8) - ANSWER-(1) acts of God or of the public enemy,
(2) acts of the Government in either its sovereign or contractual capacity,
(3) fires,
(4) floods,
(5) epidemics,
(7) strikes,
(8) freight embargoes, and
(9) unusually severe weather.

Impacts of delays - ANSWER-adversely affect the construction progress, at least
partially at fault of the owner=disputes. Amount of monetary compensation that is
justified for an owner-caused delay is difficult to asses

Time extensions - ANSWER-Must be in writing, and must be submitted within a
given time after the delay has occurred. May save a contractor money by avoiding
the costly need to accelerate work

Types of acceleration - ANSWER-Actual acceleration and constructive acceleration

Geschreven voor

Instelling
CMGT 3500 3 2025
Vak
CMGT 3500 3 2025

Documentinformatie

Geüpload op
17 oktober 2025
Aantal pagina's
6
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$8.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Freshy Oxford University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
61
Lid sinds
2 jaar
Aantal volgers
4
Documenten
6990
Laatst verkocht
2 weken geleden

3.6

10 beoordelingen

5
3
4
4
3
1
2
0
1
2

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen