the ultimate goal is to find the edge of water migration which moves in a three dimensional path
throughout the structure. this is accomplished across carpeted surfaces using a _____ and across most
hard surfaces using a _____ (non-penetrating) moisture meter. - CORRECT ANSWERS-
moisture sensor , non-invasive
water from a clean source with no substantial risk of causing sickness or discomfort is said to be -
CORRECT ANSWERS-category 1
water that has significant degree of chemical biological and or physical contamination and potential to
cause sickness or discomfort is ___________ - CORRECT ANSWERS-category 2
cleaning procedures must be employed before the drying of a category 2 water loss can continue. at a
minimum affected __________ must be removed and disposed of and carpet must be throughly cleaned
using a hot water extraction method. - CORRECT ANSWERS-carpet underlay
When water intrusion results from a grossly unsanitary source or carries __________ (disease causing)
agents, it is said to be Category 3. - CORRECT ANSWERS-pathogenic
worker and occupant ______ and safety are the 1st priority on every sewage loss. areas affected by
category 3 water intrusion are marked and posted as potentially hazardous. - CORRECT
ANSWERS-health
Various cleaning and decontamination procedures must be used on Category 3 water losses, including
the removal of all ______ ______ materials affected by the water intrusion. - CORRECT
ANSWERS-highly porous
when resistance is encountered and performing proper services in a category 3 water loss becomes a
challenge restorers _____________ immediately to prevent liability and address the conflict. -
CORRECT ANSWERS-stop work
, Third party experts are commonly referred to as Indoor Environmental Professionals, or ____. -
CORRECT ANSWERS-IEP
Losses where regulated or hazardous materials have contaminated the structure do not change the
_______ of water. - CORRECT ANSWERS-category
pre-existing conditions should be identified documented and communicated to all _________ parties
during the initial inspection. - CORRECT ANSWERS-materially interested
when carpet delimitation (the loss of integrity in the adhesives used to laminate the _____ and _____
backings) has occurred, further damage is very likely. for this reason when extensive carpet delimitation
is discovered technicians must call it to the attention go all materially interested parties , document the
condition and suggest replacement. - CORRECT ANSWERS-primary and secondary
there are number of causes for carpet delimitation - many of them relates to ____ restoration activities -
CORRECT ANSWERS-improper
Many building materials will absorb excess water vapor and suffer damage, especially when air is
allowed to remain above __% relative humidity. - CORRECT ANSWERS-60%
Hygroscopic materials gain and lose moisture continually in an effort to ________ with the water content
in the surrounding air mass. The more hygroscopic the material, the faster it will collect water vapor, and
the easier it will suffer _________ damage. - CORRECT ANSWERS-equalize and secondary
When water intrusion results in water running through wall cavities, inspection access holes are used to
ensure that blown-in insulation has not compacted and lost its ______. Wet compressed insulation
should be ______ - CORRECT ANSWERS-R-Value , removed
the most effective way to speed the drying process is to remove as much of the water in a liquid state as
possible during the _____ phase (for example multiple extractions.) poor extractions will significant slow
the drying process. - CORRECT ANSWERS-extractions