, 1 of 120
Term
A team consumes the data produced by the software written by
another team.
The 'producer' team will be ready on Day 8, but to be on the safe
side, the
'receiver' team inserts a buffer of 3 days and plans a start on Day 11.
These 3 days
between systems are called?
A. Management reserve
B.Feeding buffer
C. Backup
D. Dependency adjustments
Give this one a try later!
C D
A B
Don't know?
2 of 120
Term
On the back of the story card the acceptance test cases are found.
Who specifies
the acceptance test cases?
A. Customer
,B. The whole team
C. Test manager
D.Scrum Master
Give this one a try later!
A C
B D
Don't know?
3 of 120
Term
What is the primary role of a Product Owner?
A. The PO is basically a project manager who balances scope, time,
cost and
risk.
B.Maximizing the Return on Investment (ROI) of the software
developed.
C. People management for the Team.
D.Avoiding distracting and keeping stakeholders at bay.
Give this one a try later!
D B
, C A
Don't know?
4 of 120
Term
The Development Team is expected to have all the skills needed to:
A. Complete the project by the given deadline and budget shared
upfront with
the sponsor.
B.Do analysis and development work, but leave out all forms of
testing since
that is handled by another specialized team.
C. Turn the Product Backlog items into potentially shippable product
increments.
D.Master all state-of-the-art technology practices and tools
available.
Give this one a try later!
A C
B D
Don't know?