coordination Exam 2026 Questions and
Answers
IRO - Correct answer-Interconnection reliability operations
The reliability coordinator is responsible for - Correct answer-the reliable operation
of the bulk electric system
IRO -001 - Correct answer-authority
IRO - 003 - Correct answer-Wide area view
The RC shall know the current status of all _______ in their whose failure,
degradation or disconnection could result in a system operating limit or an
interconnection reliability operating limit violation - Correct answer-
Since events in one part of the system can influence operations in all other parts of
the system, the RC is required to monitor and determine any potential SOL and
IROL violations - Correct answer-True
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
,Once a Reliability Coordinator issues a directive to preserve the integrity and
reliability of the Bulk Electric System, actions shall be taken without delay, but no
longer than ________. - Correct answer-30 minutes
Reliability Coordinator shall initiate control actions or emergency procedures to
relieve the violation without delay and no longer than ___________. - Correct
answer-30 minutes
___________ have the duty to continuously assess transmission reliability and
coordinate emergency operations among the operating entities within the region
and across the regional boundaries. - Correct answer-Reliability Coordinators
A portion of a Reliability Coordinator Area is experiencing low voltage, what
directives should the Reliability Coordinator give? - Correct answer-Lower
transfers across area and increase generation in area with low voltage
Low voltage is a result of reactive power and losses associated with transferring
power to load areas. Increasing generation in the area with low voltage reduces
losses associated with transferring power.
At any time, regardless of prior planned or unplanned events, the Reliability
Coordinator should be able to determine any potential ______________ violations
©COPYRIGHT 2025, ALL RIGHTS RESERVED 2
, within its Reliability Coordinator Area. - Correct answer-System Operating Limits
(SOL) & Interconnection Reliability Operating Limits (IROL)
The _______ as defined by NERC is the electrical generation resources,
transmission lines, interconnections with neighboring systems, and associated
equipment, generally operated at voltages of 100 kilovolts or higher. - Correct
answer-Bulk Electric System
Each Reliability Coordinator shall have adequate analysis tools, such as state
estimation, contingency analysis capabilities and ________ to monitor the Bulk
Electric System. - Correct answer-wide-area overview displays
Wide-Area view is required therefore, each Reliability Coordinator shall have
adequate analysis tools; such as, state estimation, pre- and post-contingency
analysis capabilities (thermal, stability, and voltage), and wide-area overview
displays.
This is stated in the NERC Standard IRO-002 explicitly and applied in the NERC
Standard IRO-003 as the RC shall monitor a wide area view within its Reliability
Coordinator Area and that of neighboring Reliability Coordinators.
©COPYRIGHT 2025, ALL RIGHTS RESERVED 3