Combined Service Mains
This standard shall apply to ______ intended to carry water for fire service mains
AHJ
Working plans shall be submitted for approval to the _____ before any equipment is installed or
remodeled.
Pressure-Regulating devices
____ shall not be used
Control Valves
______ shall not be installed in the piping from the fire department connection to the fire service main
Control Valves
_____ shall be permitted in the system downstream of the fire department connection
Check Valve
When more than one water supply exists, a ___________ shall be installed in each connection