Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

AFSB 152: The Institutes Practice Exam Questions and Answers – 2025/2026 | Verified and Updated Study Guide

Beoordeling
-
Verkocht
-
Pagina's
24
Cijfer
A+
Geüpload op
22-10-2025
Geschreven in
2025/2026

This document provides the full set of verified practice exam questions and answers for AFSB 152 from The Institutes, updated for the 2025/2026 academic year. It covers key concepts related to surety bonds, underwriting principles, risk assessment, and contract obligations. Designed to mirror the actual exam format, this resource helps students master AFSB 152 content efficiently and prepare confidently for The Institutes’ certification exams.

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

AFSB 152 - The Institutes Practice Exam
Questions and Answers 2023
Lansing Construction Company completed major jobs including road grading, bridges,
and base and paving work. Which one of the following types of contractors is Lansing?
· Heavy and highway construction
· General Engineering contractor
· General Building contractor
· Design/build contractor - Correct Answer-Heavy and highway construction

The project owner for a new shopping plaza being built in Highville is the Highville
Municipal Property Company. The role of the project owner at the beginning of any
construction project is to
· Engage consultants in fields in which it lacks the expertise necessary for the project
· Define a need for a facility and engage an architect or an engineer
· Furnish an estimated project cost that may be used to negotiate financing for the
project
· Design the facility and prepare the plans and specifications for its construction -
Correct Answer-Define a need for a facility and engage an architect or an engineer

In construction contracts, the critical path method
· Ensures that, during mobilization, the crew moves big equipment from one location to
another following the shortest route, in terms of mileage
· Ensures that, during mobilization, the crew moves big equipment from one location to
another on less-used roads and during times when traffic is minimal
· Ensures that work is completed in a logical sequence and that the project is completed
within the time budget specified in the contract terms
· Ensures that all minor finishing tasks, identified in a punch list, are completed before
the project reaches substantial completion - Correct Answer-Ensures that work is
completed in a logical sequence and that the project is completed within the time budget
specified in the contract terms

The party that directly benefits from the additional security of knowing that the
contractor has satisfied the surety's comprehensive prequalification review is the
· Suppliers
· Laborers
· Project Owners
· Architect or engineer - Correct Answer-Project Owners

Private work is not bid as tightly as public work because all bidders usually understand
that a fair markup of a contractor's work is expected and that
- Numerous, unexpected change orders would become a nuisance
- The owner, architect, and contractor are likely to collaborate on a private project

,- The quality of work on private projects is expected to meet only the specific standards
- When the contractor begins to seek extras, owners and architects believe they are
being mistreated - Correct Answer-Numerous, unexpected change orders would
become a nuisance

Due to the scope of the project, Cortland Company and May Contracting agreed to a
cost-plus construction contract. Which one of the following accurately describes a cost-
plus construction contract?
- A cost-plus contract includes cost of work and a fee for overhead and profit.
- A cost-plus contract is a fixed-price contract with a changes clause.
- A cost-plus contract includes costs of materials plus labor costs.
- A cost-plus contract includes work costs agreed to in advance plus cost overruns. -
Correct Answer-A cost-plus contract includes cost of work and a fee for overhead and
profit.

Which one of the following correctly describes the right of an owner or a contractor to
terminate a contract?
- An owner or a contractor can terminate a contract at any time for any reasonable
cause.
- Without a termination clause, an owner or a contractor can terminate a contract only
for a material breach of contract.
- Without a termination clause, an owner can terminate a contract, but a contractor
cannot.
- Without a termination clause, an owner or a contractor cannot terminate a contract for
any reason. - Correct Answer-Without a termination clause, an owner or a contractor
can terminate a contract only for a material breach of contract.

A limited liability company is most similar to a:
- Subchapter S corporation.
- Subchapter C corporation.
- Joint venture.
- General partnership. - Correct Answer-Subchapter S corporation:
- Tax liability is passed through to the individual members similar to the way tax liability
is passed to shareholders in S Corps.

Mediation has become a favored form of dispute resolution. Which one of the following
statements is true regarding mediation?
- Mediation is the most time-consuming form of dispute resolution.
- Mediation encourages parties to make offers and counteroffers.
- Mediation develops a solution which is final and binding.
- Mediation often results in shock verdicts. - Correct Answer-Mediation encourages
parties to make offers and counteroffers.

Which one of the following is correct regarding the statute of limitations for filing a
lawsuit regarding a claim under the Miller Act?
- The statute of limitations is one year.

, - The statute of limitations is 90 days.
- There is no statute of limitations.
- The statute of limitations is determined by state law. - Correct Answer-The statute of
limitations is one year.

Contractor Marshall has been presented with a unit-priced contract from project owner
Grayson Properties. A unit-price contract is used
- For most construction contracts.
- To provide a sharing agreement.
- To provide a maximum guaranteed price.
- When the quantity of work cannot be determined in advance. - Correct Answer-When
the quantity of work cannot be determined in advance.

Which one of the following is true regarding joint ventures?
- All partners must participate equally in a joint venture.
- All partners are always fully responsible for the entire project.
- In a silent joint venture, the silent partner has limited responsibility.
- A limited joint venture can be formed to limit an individual's participation. - Correct
Answer-A limited joint venture can be formed to limit an individual's participation.

Which one of the following correctly describes those who must give notice to the prime
contractor under the Miller Act?
- Only second-tier claimants are required to give notice to the prime contractor.
- No one filing a claim under the Miller Act is required to give notice to the prime
contractor.
- Only first-tier claimants are required to give notice to the prime contractor.
- All claimants are required to give notice to the prime contractor. - Correct Answer-Only
second-tier claimants are required to give notice to the prime contractor.

Ewing General Contracting (EGC) entered a contract to complete a major renovation for
Ralph's Restaurant. Because Ralph's is located in a tourist town, it was important that
the construction work be completed by May 1. The construction contract included a
provision that stated that if the job was not completed by May 1, EGC would be
assessed $500 a day for each day of delay in completing the project. These damages to
be paid by EGC are known as
- Direct damages.
- Consequential damages.
- Liquidated damages.
- Actual damages. - Correct Answer-Liquidated damages.

The costliest method of contract dispute resolution is typically
- Contract termination.
- Mediation.
- Arbitration.
- Litigation. - Correct Answer-Litigation.

Geschreven voor

Vak

Documentinformatie

Geüpload op
22 oktober 2025
Aantal pagina's
24
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$13.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
TopGradeSolutions Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
95
Lid sinds
2 jaar
Aantal volgers
9
Documenten
13297
Laatst verkocht
8 uur geleden
TOPGRADESOLUTIONS

Here we offer revised study materials to elevate your educational outcomes. We have verified learning materials (Research, Exams Questions and answers, Assignments, notes etc) for different courses guaranteed to boost your academic results. We are dedicated to offering you the best services and you are encouraged to inquire further assistance from our end if need be. Having a wide knowledge in Nursing, trust us to take care of your Academic materials and your remaining duty will just be to Excel. Remember to give us a review, it is key for us to understand our clients satisfaction. We highly appreciate clients who always come back for more of the study content we offer, you are extremely valued. All the best.

Lees meer Lees minder
4.9

171 beoordelingen

5
159
4
7
3
4
2
0
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen