Another name for bar chart - Answers Gantt Chart
Bar Chart Schedule Steps - Answers - Project Duration
- Critical Activity / Path
- Floats
- Early Start Schedule
- Late
- 4 Different Relationships + Lag / Lead
Revising Bar Chart because of change order... - Answers Will be a bit difficult
Bar Chart Preparation - Answers - Identify Activities
- Estimate Activity Durations
- Develop Activity Sequence
- Construct Bar Chart
Who developed Bar Chart? - Answers Henry Gantt in 1917
Bar Chart Time Scaled - Answers Length of a bar representing a certain activity is proportional
to the duration of that activity.
What is not shown on Bar Chart? - Answers Dependency between activities
What is easy to show on Bar Chart? Why are they so popular? - Answers - Current schedule
status
- % complete
- simplistic and easy of understanding
- No calculations are involved
Disadvantages of a Bar Chart - Answers - Lack of logical representation (relationships)
- Can't understand why an activity started when it did
- Bar charts may not be practical in a project with many activities
4 types of of activity relationships: - Answers - Physical relationship