This document contains the official test bank for Information Technology Project Management (9th Edition) by Kathy Schwalbe. It includes a full collection of chapter-by-chapter exam questions with verified correct answers covering key PMBOK® Guide concepts. Topics include project integration, scope, time, cost, quality, communications, risk, resource, and stakeholder management, as well as agile methodologies and emerging technologies. Ideal for instructors, students, and PMP® certification candidates seeking a comprehensive assessment resource aligned with current project management standards.

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

TEST BANK FOR INFORMATION TECHNOLOGY PROJECT
MANAGEMENT, 9TH EDITION, KATHY SCHWALBE
Chapter 1: Introduction to Project Management


TRUE/FALSE

1. Until the 1980s, project management primarily focused on providing schedule and resource data to top
management in the military, computer, and construction industries.

ANS: T
Until the 1980s, project management primarily focused on providing schedule and resource data to top
management in the military, computer, and construction industries. Today’s project management
involves much more, and people in every industry and every country manage projects.

PTS: 1 DIF: Difficulty: Easy REF: p.2
OBJ: LO: 1-1 NAT: BUSPROG: Technology TOP: Introduction
KEY: Bloom's: Knowledge

2. A difference between operations and projects is that operations end when their objectives have been
reached, whereas projects do not.

ANS: F
Projects are different from operations in that they end when their objectives have been reached or the
project has been terminated.

PTS: 1 DIF: Difficulty: Moderate REF: p.4
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Comprehension

3. Every project should have a well-defined objective.

ANS: T
A project has a unique purpose. Every project should have a well-defined objective.

PTS: 1 DIF: Difficulty: Easy REF: p.6
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Knowledge

4. Projects should be developed in increments.

ANS: T
A project is developed using progressive elaboration. Projects are often defined broadly when they
begin, and as time passes, the specific details of the project become clearer. Therefore, projects should
be developed in increments.

PTS: 1 DIF: Difficulty: Moderate REF: p.6
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Comprehension

, TEST BANK FOR INFORMATION TECHNOLOGY PROJECT
MANAGEMENT, 9TH EDITION, KATHY SCHWALBE
5. Resources in a project should be used effectively because they are limited.

ANS: T
A project requires resources, often from various areas. Resources, however, are limited and must be
used effectively to meet project and other corporate goals.

PTS: 1 DIF: Difficulty: Moderate REF: p. 7
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Comprehension

6. A project manager’s primary role is to provide the funding for a project.

ANS: F
A project sponsor usually provides the direction and funding for a project.

PTS: 1 DIF: Difficulty: Easy REF: p.7
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Knowledge

7. One of the main reasons why project management is challenging is because of the factor of uncertainty.

ANS: T
A project involves uncertainty. Every project is unique and thus it is sometimes difficult to define its
objectives clearly, estimate how long it will take to complete, or determine how much it will cost. This
uncertainty is one of the main reasons project management is so challenging.

PTS: 1 DIF: Difficulty: Moderate REF: p.7
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Comprehension

8. Questions about how a team will track schedule performance is related to a project’s scope.

ANS: F
Project scope deals with questions such as, “What work will be done as part of the project?”, “What
unique product, service, or result does the customer or sponsor expect from the project?”, or “How will
the scope be verified?”

PTS: 1 DIF: Difficulty: Moderate REF: p.7
OBJ: LO: 1-2 NAT: BUSPROG: Technology TOP: What is a Project?
KEY: Bloom's: Comprehension

9. In order to be realistic, a project manager should always set discrete goals instead of a range of
objectives.

ANS: F
Projects involve uncertainty and limited resources. Thus they rarely finish according to their original
scope, time, and cost goals. Instead of discrete target goals, it is often more realistic to set a range of
goals.

, TEST BANK FOR INFORMATION TECHNOLOGY PROJECT
MANAGEMENT, 9TH EDITION, KATHY SCHWALBE

PTS: 1 DIF: Difficulty: Moderate REF: p.8
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Project?
KEY: Bloom's: Comprehension

10. Managing the triple constraint primarily involves making trade-offs between resources and quality.

ANS: F
Managing the triple constraint involves making trade-offs between scope, time, and cost goals for a
project. Experienced project managers know that one must decide which aspect of the triple constraint
is most important.

PTS: 1 DIF: Difficulty: Easy REF: p.9
OBJ: LO: 1-2 NAT: BUSPROG: Analytic TOP: What is a Product?
KEY: Bloom's: Knowledge

11. The only responsibility of a project manager is to meet the specific scope, time, and cost goals of a
project.

ANS: F
Project managers must strive not only to meet specific scope, time, cost, and quality goals of projects
but also facilitate the entire process to meet the needs and expectations of people involved in project
activities or affected by them.

PTS: 1 DIF: Difficulty: Moderate REF: p.9
OBJ: LO: 1-3 NAT: BUSPROG: Analytic
TOP: What is Project Management? KEY: Bloom's: Comprehension

12. A project’s stakeholders consist of its customers, users, and suppliers.

ANS: T
Stakeholders are the people involved in or affected by project activities, and include the project sponsor,
project team, support staff, customers, users, suppliers, and even opponents of a project.

PTS: 1 DIF: Difficulty: Moderate REF: p.10
OBJ: LO: 1-3 NAT: BUSPROG: Analytic
TOP: What is Project Management? KEY: Bloom's: Comprehension

13. Opponents of a project do not belong to the category of stakeholders.

ANS: F
Stakeholders are the people involved in or affected by project activities, and include the project sponsor,
project team, support staff, customers, users, suppliers, and even opponents of a project.

PTS: 1 DIF: Difficulty: Moderate REF: p.10
OBJ: LO: 1-3 NAT: BUSPROG: Analytic
TOP: What is Project Management? KEY: Bloom's: Comprehension

, TEST BANK FOR INFORMATION TECHNOLOGY PROJECT
MANAGEMENT, 9TH EDITION, KATHY SCHWALBE
14. The importance of stakeholders’ needs and expectations is limited to the beginning of a project.

ANS: F
Stakeholders’ needs and expectations are important in the beginning and throughout the life of a
project. Successful project managers develop good relationships with project stakeholders to understand
and meet their needs and expectations.

PTS: 1 DIF: Difficulty: Moderate REF: p.11
OBJ: LO: 1-3 NAT: BUSPROG: Analytic
TOP: What is Project Management? KEY: Bloom's: Comprehension

15. Project procurement management primarily involves identifying stakeholder needs while managing their
engagement throughout the life of the project.

ANS: F
Project management knowledge areas describe the key competencies that project managers must
develop. Project procurement management involves acquiring or procuring goods and services for a
project from outside the performing organization.

PTS: 1 DIF: Difficulty: Moderate REF: p.12
OBJ: LO: 1-3 NAT: BUSPROG: Technology
TOP: What is Project Management? KEY: Bloom's: Comprehension

16. The primary role of project stakeholder management is to ensure that the project will satisfy the stated
needs for which it was undertaken.

ANS: F
Project management knowledge areas describe the key competencies that project managers must
develop. Project stakeholder management includes identifying and analyzing stakeholder needs while
managing and controlling their engagement throughout the life of the product.

PTS: 1 DIF: Difficulty: Moderate REF: p.12
OBJ: LO: 1-3 NAT: BUSPROG: Technology
TOP: What is Project Management? KEY: Bloom's: Comprehension

17. Project human resource management is concerned with making effective use of the people involved
with a project.

ANS: T
Project management knowledge areas describe the key competencies that project managers must
develop. Project human resource management is concerned with making effective use of the people
involved with the project.

PTS: 1 DIF: Difficulty: Moderate REF: p.12
OBJ: LO: 1-3 NAT: BUSPROG: Analytic
TOP: What is Project Management? KEY: Bloom's: Comprehension

18. Stakeholder analyses, work requests, and project charters are tools used in integration management.

Geschreven voor

Vak

Documentinformatie

Geüpload op
25 oktober 2025
Aantal pagina's
320
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$15.99
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper
Seller avatar
TESTBANKSSTORES
4.0
(1)

Maak kennis met de verkoper

Seller avatar
TESTBANKSSTORES Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
9
Lid sinds
8 maanden
Aantal volgers
1
Documenten
1397
Laatst verkocht
3 uur geleden
TESTBANKSSTORES

Accounting, Finance, Statistics, Computer Science, Nursing, Chemistry, Biology & More — A+ Test Banks, Study Guides & Solutions As a Top 1st Seller on Stuvia and a nursing professional, my mission is to be your light in the dark during nursing school and beyond. I know how stressful exams and assignments can be, which is why I’ve created clear, reliable, and well-structured resources to help you succeed. I offer test banks, study guides, and solution manuals for all subjects — including specialized test banks and solution manuals for business books. My materials have already supported countless students in achieving higher grades, and I want them to be the guide that makes your academic journey easier too. I’m passionate, approachable, and always focused on quality — because I believe every student deserves the chance to excel. **Ace Your Exams with Confidence!**

Lees meer Lees minder
4.0

1 beoordelingen

5
0
4
1
3
0
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen