What is the MAXIMUM penalty for a contractor who undertakes work without the
proper class of license? - ANSWER: $500 fine per day for each day of violation
plus penalties for a misdemeanor.
All Class A contractor licensure applications MUST include - ANSWER:
information on the knowledge, skills, and abilities of the applicant.
What is the PRIMARY purpose of licensing? - ANSWER: Protect the health and
welfare of the public.
When a claimant is paid funds from the Contractors Recovery Trust Fund -
ANSWER: the contractor's license is revoked. !!!
The application for licensure MUST include - ANSWER: the business address of
the proposed designated employee.
Which of the following is a requirement for a joint venture? - ANSWER: Either
the joint venture or each contracting party of the joint venture must be licensed.
All of the following must be licensed EXCEPT - ANSWER: a material supplier
who advises a contractor.
How much is the Class A initial license fee? - ANSWER: $200
,2|Page
A licensee's name change MUST be reported to the Board within a MAXIMUM of
how many days? - ANSWER: 30 days
According to the Board Rules and Regulations, a full-time employee is one who
works a MINIMUM of how many hours per week? - ANSWER: 30 hours.
A firm desiring to be licensed as a Class B contractor MUST have a MINIMUM
net worth of - ANSWER: $15,000.
According to the Board Rules and Regulations, which of the following could be a
qualified individual? - ANSWER: Any full-time employee.
An appeal of the local building official's decision to refuse to grant a modification
to the USBC MUST be made to the local building board within a MAXIMUM of
how many days? - ANSWER: 90 days.
A building official MUST issue a certificate of occupancy for a building that meets
all the requirements for a certificate within a MAXIMUM of how many working
days after the certificate was requested? - ANSWER: 5
Additions to buildings MUST comply with - ANSWER: the current code for new
construction.
When MUST the work be stopped following the issuance of a stop work order? -
ANSWER: Immediately
Who is to be in charge of a local building department? - ANSWER: Building
official.
, 3|Page
Contractors who are assessed a fee to support the Transaction Recovery Fund
MUST pay this fee within a MINIMUM of how many days from when the
assessment fee notice was mailed? - ANSWER: 45 days
Contractors will be assessed a fee for the Transaction Recovery Fund whenever the
fund balance is less than - ANSWER: $400,000.
Payments made by the Transaction Recovery Fund to claimants may include an
amount for - ANSWER: attorneys' fees.
A contract for which of the following types of structures may be subject to
recovery from the Transaction Recovery Fund? - ANSWER: Residential only.
A verified claim for payment from the Transaction Recovery Fund MUST occur
within a MAXIMUM of what period of time from the date the claimant was
awarded a final judgment? - ANSWER: 12 months.
An appeal of a final decision of a county on an erosion control plan MUST be filed
within a MAXIMUM of how many days? - ANSWER: 30 days.
Temporary erosion and sediment control measures MUST be removed within a
MAXIMUM of how many days after the final site stabilization? - ANSWER: 30
days.
Which of the following statements about a sole proprietorship is TRUE? -
ANSWER: The business, or any part of it, can be sold, altered, or exchanged at
will.