If a contract awards more than $_________ per payment, the
contractor is required to have a Class A.
a. 120,000
b. 7,500
c. 750,000
d. 150,000 --CORRECT ANSWER--a. 120,000
An erosion control conservation plan needs to be approved within
____ days.
a. 18 days
b. 60 days
c. 29 days
Page 1 of 20
,d. 45 days --CORRECT ANSWER--d. 45 days
Where do you go to file an appeal of a violation to the USBC
provisions?
a. none because there is no appeal.
b. to OSHA
c. to the court
d. to the BBCA --CORRECT ANSWER--d. to the BBCA
A contractor does not notify a change of address and so does not
receive a timely Notice of Renewal. Who is responsible when the
contractor does not renew his license on time?
a. USBC
b. OSHA
c. The licensee Contractor
d. DPOR --CORRECT ANSWER--c. The licensee Contractor
A designated employee should be?
Page 2 of 20
, a. a full time worker
b. at least 18 years old, full time employee, has passed required
examination
c. at least 18 years old and 5 years experienced for class A
d. the owner --CORRECT ANSWER--b. at least 18 years old, full
time employee, has passed required examination
What is the initial Recovery Fund fee?
a. 200
b. 50
c. 0
d. 25 --CORRECT ANSWER--d. 25
If a contractor earns more than $______ per year, than the contractor
is required a Class A license.
a. 120,000
b. 7,500