Why should a non-developer have a basic understanding of application logic? --
CORRECT ANSWER--- Most projects require some changes to application
logic
- Non-developers define requirements for UI changes
- Non-developers help define requirements for Gosu rules
- Non-developers define requirements for business rules
Name two places where application logic exists. --CORRECT ANSWER--Gosu
rules
Business rules
The User Interface
Classes
Entity Names
What are two types of rules and who is responsible for developing each? --
CORRECT ANSWER--Gosu rules - developers
Business rules - non-developers
Page 1 of 52
,What is the purpose of integration? --CORRECT ANSWER--Integration allows
two systems to exchange data or perform work.
Why is it important for non-developers to have a basic understanding of
integration? --CORRECT ANSWER--Non-developers assist with documenting
requirements including data mapping between the two systems and UI changes
and communicate the requirements to developers.
Name some common examples of InsuranceSuite integrations. --CORRECT
ANSWER--User authentication
Geocoding
Check printing
Document production
Document management
Address verification
What tasks are commonly performed by non-developers for integrations? --
CORRECT ANSWER--Non-developers often prepare data mapping documents
and screen mockups needed to support integration development.
Which phases in the Guidewire project lifecycle are divided into sprints? --
CORRECT ANSWER--Inception
Development
Page 2 of 52
,Stabalization
What is the typical duration of a sprint in the Inception phase? --CORRECT
ANSWER--One week
During the Stabilization phase, what is the purpose of performance testing? --
CORRECT ANSWER--Run tests to check how well the system works in
anticipated and peak loads.
During the Deployment phase, what happens during the Pilot step? --
CORRECT ANSWER--- Allow a subset of users to use the system
- Gather feedback
- Triage feedback
- Implement changes as needed
During the support phase, who is responsible for monitoring business
processes? --CORRECT ANSWER--Support team
What are the Project Manager's responsibilities? --CORRECT ANSWER--
Support the sprint team, facilitate the agile process, enable self-organization,
resolve impediments, shield outside interference, is a participatory leader and
not a dictating manager; servant leader
Page 3 of 52
, What are the Product Owner's responsibilities? --CORRECT ANSWER--Key
stakeholder representing the voice of the customer, business authority to make
decisions (can delegate to key SMEs), shares vision with the development team,
collaborates with the teams to develop and deliver the work, defines
requirements and answers the development team's questions promptly and with
authority, responsible for signing off on user stories and defects.
What are the four main areas of configuration in a Guidewire application? --
CORRECT ANSWER--1. User Interface
2. Data Model
3. Application Logic
4. Integration
What are some of the technologies used in InsuranceSuite applications? --
CORRECT ANSWER--Page Configuration Format (PCF) files
Gosu (programming language)
What are some reasons for a non-developer to understand the technology stack?
--CORRECT ANSWER--To determine what data is stored and if new
requirements need additional data elements.
To know how and where data is used.
To communicate what data may be needed beyond what is in the base
configuration.
To determine valid values or circumstances for the new data.