1. Which of the following are typical schedules found on Door, Light Fixture, Panel-
Construction Drawing sets? board, Room finish, Win-
dow
2. The portion of the construction drawing set that in- Specifications
cludes less visual and more text based information
about a project is the
3. In the most recent reorganization of construction 26
specifications, the electrical information is found pri-
marily in section
4. TRUE or FALSE: Because there is no room allocated False
for expansion (or growth through the creation of new 23 05 33
sections) new sections can only be added at the subse-
quent of the Masterformat.
specific information and requirements for HVAC piping
heat tracing would be located in Master Format sec-
tion,,,
5. In the 2004 version, there are ? groups that contain all 2
of the subgroups. A request for an interpretation of the 01 26 13
contract that may initiate contract modification would
be explained in the MasterFormat section ?
6. true or false: in the 2004 version of MasterFormat each false
section number has four digits instead of the prior 11 23 26
versions that had six digits.
Specifications for commercial washers and extractors
would be found in MasterFormat section ?
1/8
, CML test new
Study online at https://quizlet.com/_hfgmw9
7. The masonry division is a part of the ? subgroup in Facility Construction
the 2004 MasterFormat. The Requirements for epoxy
coated reinforcing steel are located in MasterFormat 03 21 16
section ?
8. In the NIST residence, which window types are awning d
windows? Select all that apply. f
g
9. In which of the following areas is DWH-2 located? Enter In the garage
the grid location where it is located on the plan. E-103: P12
10. Which circuit number and electrical panel listed below Circuit 17, Panel RP-G
supply DWH-2? Provide the grid location where the E-103: p11
specifications for the disconnecting means are locat-
ed.
11. There is only one door type 12 used in the NIST resi- pocket
dence. What type of door is Door 12? Provide the grid E-103: P12
location where this information is given on the prints.
12. The builder must submit two 12 inch x ? samples for 8"
each type of finish coating for the architects review of 09 90 00:1.4:b:3
color and texture only. Provide the location of where
this information is found in the specifications.
13. Molded-case circuit breaker shunt trips must have 55%
120-volt coils energized from a separate circuit and set 26 24 16:2.3:b:4:e
to trip at ? of the rated voltage. Provide the location of
where this information is found in the specifications.
14. fixture support wires for humid spaces must meet the 2.68mm
following requirements: ASTM A 580/A 580M, Compo- 26 51 00:2.6:e
2/8
Study online at https://quizlet.com/_hfgmw9
1. Which of the following are typical schedules found on Door, Light Fixture, Panel-
Construction Drawing sets? board, Room finish, Win-
dow
2. The portion of the construction drawing set that in- Specifications
cludes less visual and more text based information
about a project is the
3. In the most recent reorganization of construction 26
specifications, the electrical information is found pri-
marily in section
4. TRUE or FALSE: Because there is no room allocated False
for expansion (or growth through the creation of new 23 05 33
sections) new sections can only be added at the subse-
quent of the Masterformat.
specific information and requirements for HVAC piping
heat tracing would be located in Master Format sec-
tion,,,
5. In the 2004 version, there are ? groups that contain all 2
of the subgroups. A request for an interpretation of the 01 26 13
contract that may initiate contract modification would
be explained in the MasterFormat section ?
6. true or false: in the 2004 version of MasterFormat each false
section number has four digits instead of the prior 11 23 26
versions that had six digits.
Specifications for commercial washers and extractors
would be found in MasterFormat section ?
1/8
, CML test new
Study online at https://quizlet.com/_hfgmw9
7. The masonry division is a part of the ? subgroup in Facility Construction
the 2004 MasterFormat. The Requirements for epoxy
coated reinforcing steel are located in MasterFormat 03 21 16
section ?
8. In the NIST residence, which window types are awning d
windows? Select all that apply. f
g
9. In which of the following areas is DWH-2 located? Enter In the garage
the grid location where it is located on the plan. E-103: P12
10. Which circuit number and electrical panel listed below Circuit 17, Panel RP-G
supply DWH-2? Provide the grid location where the E-103: p11
specifications for the disconnecting means are locat-
ed.
11. There is only one door type 12 used in the NIST resi- pocket
dence. What type of door is Door 12? Provide the grid E-103: P12
location where this information is given on the prints.
12. The builder must submit two 12 inch x ? samples for 8"
each type of finish coating for the architects review of 09 90 00:1.4:b:3
color and texture only. Provide the location of where
this information is found in the specifications.
13. Molded-case circuit breaker shunt trips must have 55%
120-volt coils energized from a separate circuit and set 26 24 16:2.3:b:4:e
to trip at ? of the rated voltage. Provide the location of
where this information is found in the specifications.
14. fixture support wires for humid spaces must meet the 2.68mm
following requirements: ASTM A 580/A 580M, Compo- 26 51 00:2.6:e