EXAM #1 QUESTIONS AND ANSWERS
/. As part of your ongoing personal development you have been asked to manage a
project for the first time. Which of the following would best define 'project'?
A. The procedures that must be followed in order to achieve all business goals.
B. A series of tasks that need to be completed in order to reach a specific outcome.
C. A temporary duty to complete a plan of action for a board or management team.
D. A strategy to provide information to senior staff or management team. - Answer-✅B.
A series of tasks that need to be completed in order to reach a specific outcome.
/.As part of the company's training and development programme you are creating
training materials for the project management team. What is the difference between
project management and process management?
A. They are the same as they both monitor performance.
B. One is about performance and the other is about objectives.
C. One is on-going and the other has defined start and finish times.
D. One is the monitoring of the processes and the other is task orientated - Answer-✅C.
One is on-going and the other has defined start and finish times.
/.You have been asked to lead the development of a new project for the first time and
you are researching the process involved in project management. What is scope
management within a project?
A. Scope management is the process of managing resources and identifying gaps
within project phases and the project life cycle.
B. Scope management is the process whereby the project lead identifies and analyses
project completion outcomes.
, C. Scope management is the process of identifying key project drivers and influences
particularly around stakeholders.
D. Scope management is the process whereby outputs, outcomes and benefits are
identified, defined and controlled. - Answer-✅D. Scope management is the process
whereby outputs, outcomes and benefits are identified, defined and controlled.
/.You are managing a project and will be using the agile method. Which of the following
is the best description of this?
A. The process by which projects can be delivered on time without any delays or issues.
B. The process by which projects can be monitored and the delivery of outcomes
guaranteed.
C. The process by which projects can be identified as unachievable prior to
commencement.
D. The process by which projects can be managed and implemented in small chunks of
work - Answer-✅D. The process by which projects can be managed and implemented
in small chunks of work
/.Your manager has asked you to monitor a project as part of your personal
development. Which of the following is a tool used to monitor project progress?
A. Scheduling sheet.
B. Gantt chart.
C. Resource analysis.
D. SWOT analysis. - Answer-✅B. Gantt chart.
/.As part of your new role your manager has asked you to put together a resource plan
for a project. What is the best description of project resource planning?
A. A plan of required resources to meet the needs of a project.
B. A plan of the staffing resources required over a specific time period.
C. A plan for allocating tasks and activities to project contributors.
D. A plan of financial commitments and outlays within a project scope. - Answer-✅A. A
plan of required resources to meet the needs of a project.