1. What is the primary regulatory authority governing well construction
and drilling in New Jersey?
A. NJ Department of Environmental Protection (NJDEP)
B. NJ Department of Labor
C. NJ Department of Agriculture
D. US Environmental Protection Agency
Answer: A
Rationale: The NJDEP regulates all well drilling, installation, and
abandonment in New Jersey under the NJ Well Construction and
Maintenance Regulations.
2. What does “VCLG” stand for in the context of New Jersey well drilling
licenses?
A. Vertical Closed Loop Geothermal
B. Variable Control Logging Grade
C. Vertical Casing Lining Guide
D. Ventilation Control Layer Grid
Answer: A
Rationale: VCLG refers to Vertical Closed Loop Geothermal systems,
, which are specialized geothermal heat exchange wells regulated by
NJDEP.
3. A licensed well driller in NJ must renew their license how often?
A. Every year
B. Every two years
C. Every three years
D. Every five years
Answer: B
Rationale: NJ well drilling licenses are renewed biennially to ensure
continued professional competency and compliance.
4. Before drilling a geothermal borehole, a driller must first:
A. Obtain a zoning permit
B. Notify the NJDEP and obtain a permit number
C. File with the county clerk
D. Submit to the local health board only
Answer: B
Rationale: NJDEP requires notification and permit issuance before any
well or borehole construction activity.
5. The required setback distance between a potable water well and a septic
tank in NJ is:
A. 10 feet
B. 25 feet
C. 50 feet
D. 100 feet
Answer: C
Rationale: NJ regulations specify a 50-foot minimum separation between
potable wells and septic systems to prevent contamination.
, 6. When constructing a geothermal loop, what type of piping material is
typically required?
A. PVC Schedule 40
B. HDPE SDR 11 or SDR 13.5
C. Copper tubing
D. Cast iron pipe
Answer: B
Rationale: HDPE piping is approved for geothermal loops due to its
durability, flexibility, and heat transfer properties.
7. A VCLG driller must submit well completion reports within how many
days of project completion?
A. 7 days
B. 14 days
C. 30 days
D. 60 days
Answer: C
Rationale: NJDEP mandates submission of completion reports within 30
days for recordkeeping and compliance tracking.
8. The NJDEP Division of Water Supply and Geoscience is responsible for:
A. Inspecting septic tanks
B. Regulating pesticide applications
C. Overseeing groundwater and well drilling activities
D. Issuing building permits
Answer: C
Rationale: This division handles groundwater protection, well licensing,
and regulatory compliance for drilling operations.
9. What is the purpose of grouting in a VCLG borehole?
A. To lubricate the drill bit
B. To prevent vertical movement of groundwater