Elements needed prior to steel erection: - Site layout plan, site specific erection plan, and
construction sequencing plan
Before authorizing the start of steel erection, the *blank* shall provide the steel erector with a
written notification - Controlling contractor
What subpart is steel erection? - R
Christmas treeing limits: A max of *blank* members rigged *blank* feet apart are hoisted per
lift. - 5 members
7 ft
Members being lifted are attached at: - The center of gravity and at a maintained level.
Members of the assembly should be set from: - the bottom up
Structural steel assembly:
Not more than *blank* floors between erection floor and uppermost permanent floor.
No more than *blank*, whichever is less, of unfinished bolting/welding - 8 floors
4 floors or 48 ft
All columns must be anchored by a minimum of: - 4 anchor bolts