Which of the following would be considered a primecontractor?
Ans: D. A contractor with whom the project owner has
established a contract.
Which of the following correctly identifies what is included in
legitimate labor costs? Ans: D. Hourly wages, fridge benefit
packages, payroll taxes insurance and safety costs, and small tools
and consumables
Which in the following best illustrates the PRIMARY role of a
foreman? Ans: B. To Effectively manage and lead the crew
As a foreman what should ALWAYS be your FIRST priority when
planning a job? Ans: D. Keeping the crew actively engaged in
completing their work
© 2025 All rights reserved
, 2 | Page
As a foreman what should ALWAYS be your FIRST priority when
planning of a project? Ans: B. Developing a job strategy before
the job begins
Which of the following describe the purpose of Short Interval
Planning or Look ahead planning? Ans: A. Breaking the job into
small manageable pieces
Which of the following is the FIRST thing a foreman must do
before beginning to plan a job? Ans: A. Read all the project-
related documents
Which of the following provides the BEST example of
prefabrication? Ans: A. To Create a product in the shop and
install it in the field
Which of the following is NOT required on a daily log? Ans: C.
The work completed by the individual crew members
© 2025 All rights reserved
, 3 | Page
Which of the following is NOT likely to lead to improved material
handling? Ans: D. Have all the materials and equipment delivered
at the beginning of the job
Which of the following purchasing procedures is MOST likely to
reduce material handling time? Ans: A. Bag and Tag all materials
as appropriate
What should a foreman do if damage to he/she is discovered
AFTER the delivery driver has left the job site? Ans: C. Notify the
Project manager and note the damage on the daily log.
Which of the following location represents the BEST place to store
job site materials in a manner that enhance says productivity?
Ans: D. As close to the point of installation as possible
With which of the following costs should a foreman be MOST
concerned? Ans: A. Labor
Which of the following is NOT considered a DIRECT job cost? Ans:
D. Home office overhead