A fill line in an oil burner system is a line used to: - . .
ANSWER ✔ ✔Fill the storage tank with oil.
The aquastat is located - . . ANSWER ✔ ✔Below the water
line.
All heating, combustion, and cooking equipment shall be
installed with adequate clearances from _______
construction. - . . ANSWER ✔ ✔Combustible
The equipment must be provided with ______ or the
building construction shall be _____ _____. - . .
ANSWER ✔ ✔Insulation.
Fire Protected
,2|Page
During operation the surface of combustible construction
materials will not be raised to a temp higher than _____
degrees F. - . . ANSWER ✔ ✔170 degrees
Equipment shall be so that the means of access for
ordinary operation and maintenance will not be
_______. - . . ANSWER ✔ ✔Hazardous
Acceptance Tests:
Boilers shall not be placed in operation until they have
been _____ and ____ and an equipment ____ _____
has been issued by the ______. - . . ANSWER ✔
✔Inspected and tested.
Use permit, commissioner
Periodic Inspections: All boilers must be inspected at least
_____ a _____ including chimney connections. - . .
ANSWER ✔ ✔Once a year
Owners Annual Statement: The owner of each boiler shall
file an _____ written statement with the ________,
specifying the _____of each boiler and ______ for
, 3|Page
inspection. - . . ANSWER ✔ ✔Annual, commissioner,
location, arrangement.
Field Tests: all piping and oil storage tanks shall be
_______ tested for tightness by the ______ before the
system is operated. - . . ANSWER ✔ ✔Hydrostatically,
contractor
The piping shall be tested at _____ times the max
working pressure applicable to that part of the piping
system but at a pressure ____ than the test pressure
required for the storage tank. - . . ANSWER ✔ ✔1/2, less
The min pressure for testing tanks shall be ____ times the
max working pressure but in no case less than ____ psi. -
. . ANSWER ✔ ✔1 1/2, 25 psi
The hydrostatic pressure must be maintained until all
____ and _____ have been visually inspected for ___,
but in no case less than _____ hour. - . . ANSWER ✔
✔Joints, connections, leaks, 1/2 hour.