1. The footing or anchorage for scaffolds must be capable of carrying the
maximum intended load without
Answer Tying or guying
2. Erectors of a scaffold who exposed to potential falling object hazards shall be
provided with
Answer Over head protection
3. Osha requires a rest landing at intervals not exceed
Answer 35 feet
4. The top handrail of a scaffold must be able to withstand how many pounds
of pressure?
Answer 200
5. When Building a scaffold inside a "goggle area"
Answer Everyone inside the area must wear goggles
6. The ladder should be located on a mobile scaffold will not
1/
26
, Answer tip over
7. When should ties be installed?
Answer During the erection process
8. What body produces the primary Code or regulations guiding the scaffolding
industry?
Answer OSHA (Occupational Safety and Healthy Agency)
9. What should be used to erect scaffolding on uneven ground?
Answer Leveling Jacks
10. OSAH specifically prohibits the use of?
Answer Lean to scattolds
11. Boards or wooden pad placed on the soil to support scaffold legs are?
Answer Mudsills
12. The tube of a tube and clamp scaffold is normally what size O.D.?
Answer 1.9 Inches
13. Scaffold decks that overlap a minimum of how many inches, unless secured
2/
26
, in some other way?
Answer 12
14. the bearer in a tube and clamp scaffold is always?
Answer Placed above the adjacent runner.
15. What must a rolling scaffold have on each caster or roller?
Answer Positive locking device
16. Who must inspect a scaffold each work shift and after any occurrence which
could effect a scaffold's structural integrity?
Answer Competent person
17. What is the minimum tensile strength of D-rings and snap hooks on a safety
harness?
Answer 5,000 pounds
18. What part of the picture is identified by the letter "G"?
Answer Sill or mudsill
19. what part of the scaffold is identified by letter "A"?
3/
26