ICC VAPOR RECOVERY VT EXAM NEWEST 2025/2026 ACTUAL EXAM
WITH COMPLETE QUESTIONS AND CORRECT DETAILED ANSWERS
(100% VERIFIED ANSWERS) |ALREADY GRADED A+| ||PROFESSOR
VERIFIED||
If motor fuel accidentally comes in contact with your eyes, ensure
you flush your eyes with water for ____ min and seek medical
attention. - ANSWERS-15
The shear section of the Vapor Shear Valve must be positioned
within ___ in above or below the level of the top surface of the
dispenser island. - ANSWERS-½ in
if the flow rate at the dispenser is less than 6.5 GPM replace the
following. - ANSWERS-Fuel filters
ESO does not disconnect power to the following: - ANSWERS-
Monitoring Device
A space that is not designed for continuous employee occupancy.
- ANSWERS-Confined Space
,2|Page
Where should the PV vent be tightened? - ANSWERS-With a
suitable wrench from the screw above the cap
A Phil Tite rotatable adaptor shall be tightened to a torque
between ___ and ___ lbs. - ANSWERS-50 to 75 foot lbs
When installing the OPW drop tube seal the following shall be
observed: - ANSWERS-Install the install with the special designed
drop tube o-ring seal with the flat side against the drop tube flare
Type of sealant you should you use on a Phil-Tite Ball Float
nipple: - ANSWERS-Pipe dope
Number of open valves on the clean air separator: - ANSWERS-
One
You must be CERTIFIED by Healy to re-connect a Healy
breakaway, True or False? - ANSWERS-False
The type of pressure gauge is recommended to test Healy Vac -
ANSWERS-SYSA gauge measuring 0-100 WC
, 3|Page
On new construction, after July 1, 2004, Can you install an in-
ground Spill Bucket? - ANSWERS-YES-When Piping is monitored
and with VAC
According to Executive Order 201 - Healy P/V Valve should be
torqued at - ANSWERS-20-50 ft-lbs
For a fire to burn, these (3) three primary elements must exist: -
ANSWERS-Fuel, Oxygen, Ignition Source
When working with Electrical - Lock Out Tag Out procedures are
under these guidelines. - ANSWERS-CAL-OSHA
Organization that certifies vapor recovery systems. - ANSWERS-
CARB or ARB
According to RP 500, a level II technician may NOT inspect this
part. - ANSWERS-Replace VP 1000 Healy Pump