In a one-machine system, the order in which Jons are processed has no effect on total
time to completion
a. true
b. false - CORRECT ANSWER-a. true
In a one-time machine system, the shortest processing time sequencing rule performs
well to reduce overall job lateness
a. true
b. false - CORRECT ANSWER-a. true
in a two-machine system, the order in which jobs are processed has no effect on total
time to completion
a. true
b. false - CORRECT ANSWER-b. false
which of the following are sequencing rules used in practice?
I. first come/ first served
II. earliest due date
III. Least work remaining
a. I only
b. I and II only
c. I and III only
d. I, II, and III - CORRECT ANSWER-d. I, II, and III
Updating order due dates to reflect changes in conditions always improves shop-flow
performance.
a. True
b. False - CORRECT ANSWER-b. false
production activity control pertains mainly to activities that take place in the MPC
engine.
a. true
b. false - CORRECT ANSWER-a. true
BRAINSCAPE1
, BRAINSCAPE1
Productions activity control's main link with the rest of the MPC system is
a. detailed capacity planning
b. detailed material planning
c. material and capacity plans
d. master production scheduling - CORRECT ANSWER-a. detailed capacity planning
the shop-floor system is kept current on changes to the material plan by the MRP
system.
a. true
b. false - CORRECT ANSWER-b. false
Formal Shop-Floor control systems are necessary in a just-in-time (JIT) system.
a. true
b. false - CORRECT ANSWER-b. false
vendor scheduling is critical in a JIT system.
a. true
b. false - CORRECT ANSWER-a. true
the prime objective of production activity control is
a. meeting MPC plans
b. efficient use of capacity
c. efficient use of labor
d. efficient use of materials - CORRECT ANSWER-b. efficient use of capacity
good production activity control design and practice can compress run time.
a. true
b. false - CORRECT ANSWER-a. true
a visual representation of the scheduling process can be provided by
a. priority sequencing rules
b. a Gantt chart
c. poke-yoke
d. capacity requirements planning - CORRECT ANSWER-b. a Gantt chart
priority sequencing rules determine which of the following?
I. allocation of goods to customers
II. which machine(s) to service next
III. which job(s) to run at a work center
a. I only
b. II only
c. III only
d. I, II, and III - CORRECT ANSWER-c. III only
The "order slack" priority sequencing rule schedules the job with the least slack to be
run first.