Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

BUSI 313 - Exam 2 Study Guide Questions and Correct Answers.

Beoordeling
-
Verkocht
-
Pagina's
5
Cijfer
A+
Geüpload op
12-11-2025
Geschreven in
2025/2026

Apportionment - Answer Costs allocated to a specific segment of a project by using a % of planned total cost. Bottom-up Estimates - Answer Detailed estimates of work packages usually made by those who are most familiar with the task (also called micro estimates). Delphi Method - Answer A group method to predict future events - e.g., time, cost. Direct Costs - Answer Costs that are clearly charged to a specific work package (usually labor, materials, or equipment). Function Points - Answer Points derived from past software projects to estimate project time and cost, given specific features of the project. Learning Curve - Answer A mathematical curve used to predict a pattern of time reduction as a task is performed over and over. Overhead Costs - Answer Typically organization costs that are not directly linked to a specific project. These costs cover general expenses such as upper management, legal, market promotion, and accounting. Overhead costs are usually charged per unit of time or as a percentage of labor or material costs. Phase Estimating - Answer This estimating method begins with a macro estimate for the project and then refines estimates for phases of the project as it is implemented. Range Estimating - Answer An estimating technique in which multiple estimating points are given based on some logic (i.e. high vs. low or best case, worst case, and most likely case) Ratio Methods - Answer Uses the ratio of past actual costs for similar work to estimate the cost for a potential project. This macro method of forecasting cost does not provide a sound basis for project cost control since it does not recognize differences among projects. Reference Class Forecasting - Answer A sophisticated forecasting method in which you take an external view and forecast project costs based on actual outcomes of similar projects.

Meer zien Lees minder
Instelling
Vak

Voorbeeld van de inhoud

BUSI 313 - Exam 2 Study Guide
Questions and Correct Answers.
Apportionment - Answer Costs allocated to a specific segment of a project by using a % of
planned total cost.



Bottom-up Estimates - Answer Detailed estimates of work packages usually made by those
who are most familiar with the task (also called micro estimates).



Delphi Method - Answer A group method to predict future events - e.g., time, cost.



Direct Costs - Answer Costs that are clearly charged to a specific work package (usually labor,
materials, or equipment).



Function Points - Answer Points derived from past software projects to estimate project time
and cost, given specific features of the project.



Learning Curve - Answer A mathematical curve used to predict a pattern of time reduction as a
task is performed over and over.



Overhead Costs - Answer Typically organization costs that are not directly linked to a specific
project. These costs cover general expenses such as upper management, legal, market
promotion, and accounting. Overhead costs are usually charged per unit of time or as a
percentage of labor or material costs.



Phase Estimating - Answer This estimating method begins with a macro estimate for the
project and then refines estimates for phases of the project as it is implemented.



Range Estimating - Answer An estimating technique in which multiple estimating points are
given based on some logic (i.e. high vs. low or best case, worst case, and most likely case)



Ratio Methods - Answer Uses the ratio of past actual costs for similar work to estimate the
cost for a potential project. This macro method of forecasting cost does not provide a sound
basis for project cost control since it does not recognize differences among projects.

, Template Method - Answer Use of a prepared form to develop project networks, costs, and
time estimates.



Time and Costs Databases - Answer Collection of actual verses estimated times and costs of
work packages over many projects that are used for estimating new project tasks and their
expected possible error.



Top-Down Estimates - Answer Rough estimates that use surrogates to estimate project time
and cost (also called macro estimates).



White Elephant - Answer A burdensome possession which is not easily disposed of and whose
cost (particularly upkeep) is out of proportion with its usefulness.



Activity - Answer Task(s) of the project that consumes time while people/equipment either
work or wait.



AOA - Answer Activity-on-arrow method for drawing project networks. The activity is shown as
an arrow.



AON - Answer Activity-on-node method for drawing project networks. The activity is on the
node (rectangle)



Burst Activity - Answer An activity that has more than one activity immediately following it.



Concurrent Engineering - Answer Cross-functional teamwork in new-product development
projects that provides product design, quality engineering, and manufacturing process
engineering all at the same time.



Critical Path - Answer The longest activity path(s) through the network. The critical path can
be distinguished by identifying the collection of activities that all have the same minimum slack.



Early Time - Answer The earliest an activity can start or finish based on network logic, the data
date, and any schedule constraints



Free Slack - Answer The maximum amount of time an activity can be delayed from its early

Geschreven voor

Instelling
Vak

Documentinformatie

Geüpload op
12 november 2025
Aantal pagina's
5
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$13.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
TestSolver9 Webster University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
898
Lid sinds
2 jaar
Aantal volgers
127
Documenten
28880
Laatst verkocht
1 dag geleden
TESTSOLVER9 STORE

TOPNOTCH IN LEARNING MATERIALS,(EXAMS,STUDYGUIDES NOTES ,REVIEWS,FLASHCARDS ,ALL SOLVED AND PACKAGED.OUR STORE MAKE YOUR EDUCATION JOURNEY EFFICIENT AND EASY.WE ARE HERE FOR YOU FEEL FREE TO REACH US OUT .

3.5

156 beoordelingen

5
67
4
20
3
27
2
13
1
29

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen