Choice and Conceptual Actual Frequently
Tested Exam Questions With Reviewed
100% Correct Detailed Answers
Guaranteed Pass!!Current Update!!
1. Fire alarm equipment must be designed and tested so that it is capable of
performing at_______ nameplate input voltage.
a) 80%
b) 75%
c) 110%
d) 115% - ANSWER 110%
2. Abandoned fiber optic cables must be removed unless?
a. There is a service coil
b. Cable has connectors attached
c. Tagged for future
d. Labeled: Do Not Remove - ANSWER C
3. According to the IBC, activation of a duct smoke detector shall initiate a visible
and audible ______ signal at a constantly attended location?
a) Alarm
b) Trouble
c) Supervisory
d) HVAC - ANSWER Supervisory
, 4. Continuous load is a load on a circuit where the maximum current is expected
to be continuous for a minimum of_______
A. two hours or more
B. three hours or more
C. four hours or more
D. six hours or more - ANSWER B
5. What size copper bonding jumper must he connected between the
communications grounding electrode and power grounding electrode system?
a) 12 AWG
b) 10 AWG
c) 8 AWG
d) 6 AWG - ANSWER 6 AWG
6. Initiating, notification, and signaling line circuits will be designated by_______,
depending upon the circuit's capability to continue to operate during a specified
fault condition.
a) Type
b) Class
c) Style
d) Design - ANSWER Class
7. Smoke alarms and smoke detectors are designed to detect abnormal quantities
of smoke or fire signatures. They must operate in normal environmental
conditions and comply which applicable standard?
A. ANSI/UL 426
,B. ANSI/UL 268
C. ANSI/UL 391
D. ANSI/UL 425 - ANSWER B
8. The interior of enclosures or raceways installed underground shall be
considered to be a_______.
a) wet location
b) damp location
c) moist location
d) dry location - ANSWER Wet location
9. Fire alarm systems are required to be installed, tested, and maintained per
the_______.
A. Authority Having Jurisdiction
B. Engineered Drawings
C. Building Owner
D. Manufacturer's Instructions - ANSWER D
10. What type of smoke detector would work the best in areas with higher
temperature, higher air velocity, or humid conditions?
a) Spot type smoke detector
b) Ionization detector
c) Beam detector
d) Air sampling - ANSWER Air Sampling
, 11. In the event of a power failure, legally how long is standby power required to
be available?
60 seconds
90 seconds
10 minutes
24 hours - ANSWER 60 seconds
12. What term best describes the following phrase; on or attached to the surface
or behind access panels that are meant to allow access.
exposed
uncover
accessible
concealed - ANSWER Exposed
13. When a metal wireway contains splices and taps, the conductors, splices and
taps shall not fill the wireway to more than____of its area at that point.
20%
30%
40%
75% - ANSWER 75%
14. If more than one electrode is used, each electrode of the grounding system
must not be less than_______from any other electrode of another grounding
system.