Existing Veg, Desc/Purp ✔Correct Answer-temp or perm bmp desi to stab soil and remove sups
part from sheet flow runoff.
Existing Veg, Objectives ✔Correct Answer-1) Site Plan and Mang
2) Erosi Cont
3) Sedi Cont
4) Post-Cons Mang
Existing Veg, applic ✔Correct Answer-1) Areas within site where no const activity is occur
2) Areas where local, state and fed govt require preservation
3) Areas where existing veg can be utilized for eros, sedi, and storm water quality.
Existing veg: inspection ✔Correct Answer-1) Accord to regu timetables
2) erosi and damage veg
3) sufficient moisture to ensure growth
4) veg is well stab
5) adequate cover
6) debris and litter
7) invasive exotics
Existing veg: maint ✔Correct Answer-1) only disturb area for construct
2)irrigate dry seasons
3) remove see, and replant if need be
4) replant or rework buffer strips
5) mow and cut perennial weeds
6) remove all trash and debri
7) treat invasive and noxious species
Sched/Sequ, purp/descrip ✔Correct Answer-Temp, procedural control that involves creating a
written plan to address neck bmps and sequencing of construct activities to mitigate the erosive
effects of wind,water and construct activities.
Sched/Sequ: object ✔Correct Answer-1) site planning & management
2) erosion control
3) sediment control
Sched/Sequ: applications ✔Correct Answer-1) develop timetables for certain activities, paretic
during rainy season
Sched/Sequ: inspect ✔Correct Answer-1) inclusion of sched/seq as a bmp in the plan
2) ached site activities mirroring ached activites.
Sched/Sequ: maintanence ✔Correct Answer-1) modify ached of active when changes are
warranted
2) modify ached of active prior to rainy season to reflect updated bmp info
,Hydroseed: Des& purp ✔Correct Answer-Temp or perm bmp designed to reduce erosion and
runoff by applying mix of seed, fert and stabilizing emulsion.
Hydroseed: object ✔Correct Answer-1) erosion control
2) good housekeeping/ materials management
3) post construct management
Hydroseed: targeted pollut ✔Correct Answer-1) sediment
2) nutrients
3) metals
4) ph
Hydroseed: imp consid ✔Correct Answer-1) need adequate moisture
2) additional mulch may be added
3) pretreatment where cover is not met
4) apply from multi angles to avoid shadowing
Hydroseed: limitations ✔Correct Answer-1) seed mix approp for seasonal conditions
2) time of application per seasonal conditions
3) difficult on steep slopes
4) no pedestrian or vehicle traffic
5) avoid high winds
Hydroseed: inspect: ✔Correct Answer-1) adequate coverage of diet areas
2) signs of pedest or vehicle traffic
3) signs of animal activity
4) check seed mix for correct type and application rate
Hydroseed: Maint ✔Correct Answer-1) reapply in areas needing more cover
2) insure proper moisture
3) maintain unbroken coverage through out project
4) require repair due to traffic or animals
Hydroseed: potentailly assoc bmps ✔Correct Answer-1) hydromulch
2) seeding
3) mulching
4) temp stabi
5) tackifiers
RCP: descript and purp ✔Correct Answer-temp or perm erosion control blankets that act as soils
stabilization devices to protect diet areas from erosions.
RCP: object ✔Correct Answer-1) erosion control
2) runoff control
3) post construct
RCP: target pollutants ✔Correct Answer-1) sediment
RCP: applications ✔Correct Answer-1) on slopes w/ potential for erosion
2) flow velocity reduction
3) temp channel stab
, 4) soil/rip-rap seperator
5) soil stabi
6) aid in germination
7) increase soil infiltration
8) stockpile protect
RCP: limitations ✔Correct Answer-1) ped and vehic hazard
2) not for use in rocky, established veg will be mowed and high fire
3) blankets dislocated easily
4) uv degradable
5) small animals can be trapped
RCP: imp consid ✔Correct Answer-1) material depends on site
2) soils should be prop prepared
3) instal per manufact recommedations.
RCP: inspect ✔Correct Answer-1) sufficient staples
2) provide anchoring and overlap
3) insure direct contact with soil surface
4) no rips or tears
5) verify rcp meets plan/swpp specifications.
RCP: Maint ✔Correct Answer-1) direct contact with recp and soil
2) repair/reinstall where needed
3) repair rills or gullies
4) replace staples where needed
5) material may get entangled in mowers
RCP: potential assoc bmps ✔Correct Answer-1) seeding
2) swales
3) filter strips
4) diversions
Bmps used for erosion control ✔Correct Answer-1) hydromulch
2) Hydroseed
3) Mulching
4) RECP
5) seeding
6) Sod
7) Soil binders
8) surface roughening
9) tackifiers
What are best management practices? ✔Correct Answer-1) site planning and management
2) erosion controls
3) sediment controls
4) runoff controls
5) good housekeeping/ materials management
6) post construct management
Bmps designed for sediment control ✔Correct Answer-1) baffles