H2 Production planning system

Priority (demand): relates to what products are needed, how many are needed and when they are
needed.

Capacity: the capability of manufacturing to produce goods and services.

 The strategic business plan
This is a statement of the major goals and
objectives the company expects to
achieve over the next 2 to 10 years or
more. It has four directions: marketing,
finance, production and engineering.
 The production plan (sales &
operations plan)
Production management is concerned
with the following:
 the quantities;
 desired inventory levels;
 the resources of equipment;
 the availability of the resources needed.
Production planners must devise a plan to satisfy market demand within the resources available to
the company. There must be a balance between priority and capacity.

 The master production schedule (MPS)
The MPS is a plan for the production of individual end items. It breaks down the production plan to
show, for each period, the quantity of each end item to be made. The MPS is developed for
individual end items (each model of tricycle).

 The material requirements plan (MRP)
The MRP is a plan for the production and purchase of the components used in making the items in
the master production schedule. It shows the quantities needed and when manufacturing intends to
make or use them.

 Purchasing and production activity control (PAC)
This represents the implementation and control phase of the production phase of the production
planning and control system. Purchasing is responsible for establishing and controlling the flow of
raw materials into the factory. PAC is responsible for planning and controlling the flow of work
trough the factory.

 Capacity management
At each level of the planning and control system, reconciliation with resources must be made (must
obtain the right resources or change plan).
Inadequate resources = missed production schedules. Resources significantly exceed planned
production = idle resources.

Sales and operation planning (SOP): represents a plan by realizing the strategic plan by setting and
achieving objectives and to give feedback to revise (corrigeren) the strategy. Multidisciplinary: sales.
Marketing, R&D, production, maintenance, procurement, HRM and finance.

Sales and operations planning has several benefits:



1

,  Updating the strategic business plan;
 Managing change;
 It ensures that the various department plans are realistic and coordinated and support the
business plan;
 Provides a realistic plan that can achieve the company objectives.
 It permits better management of production, inventory and backlog.

The S&OP plan doesn’t focus on producing a high-level plan for the use of company resources but on
producing a high-level plan for the use of company resources.

Als prioriteiten aangepast moeten worden op een planning level door capaciteitsproblemen dan
wordt dat weer teruggeworpen op de andere levels.

MRP II: this provides coordination between marketing and production. It’s a fully integrated planning
and control system.

MRP systems evolved two changing conditions:
1. Computers and information technologies (IT).
2. Movement toward integration of knowledge and decision making in all aspects of direct and
indirect functions.

ERP: this is similar to the MRP II except it does not dwell on manufacturing (staat niet stil bij
fabricage). Many ERP systems are capable of allowing managers to share data between firms,
meaning that these managers can potentially have visibility across the complete span of the supply
chain.

Dingen die aangepast kunnen worden om meer vraag aan te kunnen:
 People can be hired and laid off, adding shifts/overtime and short time.
 Inventory can be build up
 Work can be subcontracted of extra equipment leased.

Basic production plan strategies:
 Chase: vary production rates to meet changes in demand. Often used when inventory cannot
be used or when resources are flexible and inexpensive to change (inventories can be kept to
a minimum).
 Level: establish average demand level and set production rate that level. Often used when
resources difficult or very expensive to change.
 Hybrid: use a combination of some chase and some level.
 Subcontracting: always producing at the level of minimum demand and meeting any
additional demand trough subcontracting. This means buying extra amounts demanded or
turning away extra demand. The major advantages are production cost, but buying extra
amounts can be greater than plants (fabriek).

Backlog: this is for delivery in the future and does not represent orders that are late or past due.

Resource planning: once the preliminary production plan is established, it must compared to the
existing resources of the company. 2 questions could be asked:
1. Are the resources available to meet the production plan?
2. If not, how will the difference be reconciled?




2

Gekoppeld boek

Geschreven voor

Instelling
Studie
Vak

Documentinformatie

Heel boek samengevat?
Ja
Geüpload op
22 juli 2014
Aantal pagina's
16
Geschreven in
2012/2013
Type
SAMENVATTING
$5.37
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
Judithbier Hogeschool van Amsterdam
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
62
Lid sinds
11 jaar
Aantal volgers
44
Documenten
10
Laatst verkocht
7 jaar geleden

3.0

2 beoordelingen

5
0
4
0
3
2
2
0
1
0

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen