QUESTIONS AND ANSWERS 100% CORRECT
⩥ 1. commissioning starts at the inception of a building project during
the pre-design phase, and continues through the post-acceptance phase.
2. provides an opportunity to cultivate a quality management focus
among all design and construction team members as they become
involved with the project. Answer: Comprehensive Commissioning
⩥ Chapter 5. Answer: Which Chapter of the ACG guideline identifies
detailed methodology for Comprehensive HVAC Commissioning?
⩥ Pre-design
Design
Construction
Acceptance
Post Acceptance. Answer: What are the Comprehensive Commissioning
phases?
⩥ 1. Commissioning established as integral part of project
2. The owner selects the commissioning authority
3. Develop the scope of commissioning
, 4. Commissioning authority reviews design intent document. Answer:
Comprehensive Commissioning: Pre-design phase
⩥ 1. Review design to ensure it accommodates commissioning
2. Write commissioning specifications defining contractor
responsibilities
3. Commissioning authority writes the commissioning plan
4. Establish the project schedule. Answer: Comprehensive
Commissioning Design phase
⩥ 1. Commissioning authority reviews contractor submittals
2. Commissioning authority updates commissioning plan
3. Commissioning process is coordinated—through project
schedule, commissioning plan and commissioning plan
and commissioning meetings
4. Carry out and document system verification checks
5. Carry out the document equipment and system start-ups
6. TAB agency completes and documents TAB work. Answer:
Comprehensive Commissioning Construction phase
⩥ 1. Carry out FPTs on all HVAC systems
2. Train the O&M staff for effective, ongoing operations and
maintenance of all systems