CORRECT ANSW....
The 1970's law that set into place the regulation of stormwater is: Answer -
The Clean Water Act
Requirements for managing stormwater activity on a construction site are
outlined in the following regulation: Answer - NPDES
Which of the following is never an allowable stormwater discharge from a
construction site? Answer - Discharge from contaminated groundwater
The Notice of termination can filed when: Answer - All construction activity,
inside and outside the building, is complete and permanent stabilization
verified
Relative to stormwater permitting, all of the following must occur before
construction starts except: Answer - Submit the notice of termination (NOT)
Which erosion control best mgmt practice increases water infiltration,
dissipates rainfall energy and slows overland flow of stormwater Answer -
Vegetation
Of the following factors that influence erosion rates, the one a contractor has
the most control over is: Answer - Groundcover