Estimating Test #1 Questions with Answers
(100% Correct Answers)
What information is contained in the working drawings? Answer: Actual
drawings that contain: dimensions and location of buildings elements,
materials required, how its assembled
What information is contained in the specifications? Answer: quality of
materials and their performance
What additional skills must the estimator have to be able to take a quantity
survey and turn it into a detailed estimate? Answer: from looking at drawings
be able to visualize the project through different phases of construction
good knowledge of job conditions and the handling of different materials
knowledge of labor performance
keep a database of information on costs
be able to use computer hardware and software
meet bid deadlines in a calm manner
What are the contract documents, and why are they so important? Answer:
comprise the owner-contractor agreement, general conditions of the contract,
the supplementary general conditions, drawings and specs
With separate contracts, describe three options available to the owner for
managing the contractor's work on the project. Answer: Owner may the general
contractor to coordinate the work, architect or engineer, or handle it themselves
List and briefly define the types of agreements that may be used for the owner's
payment to the contractor. Answer: lump sum-set price agreed upon through
competitive bidding or a negotiated price