Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

CNST 1361 Final Exam Questions with Correct Answers Latest Update 2025/2026

Beoordeling
-
Verkocht
-
Pagina's
8
Cijfer
A+
Geüpload op
22-11-2025
Geschreven in
2025/2026

CNST 1361 Final Exam Questions with Correct Answers Latest Update 2025/2026 Unit price estimate - Answers Which type of estimate is the most accurate? Advanced Work Packaging - Answers What does AWP stand for? Lower initial cost. - Answers Which of these is not a reported benefit of AWP by the industry? Construction Work Area - Answers The portion of the plot plan that has been defined jointly by Engineering and Construction that represents a logical physical envelope of work is called: Installation Work Package. - Answers The portion of work that contains all the necessary elements for a single construction crew to complete that portion of the work is called: Construction Work Package. - Answers The logical subdivision of a CWA construction scope into a defined geographic area and discipline is called: Work Breakdown Structure. - Answers The framework that represents the way a project is defined, planned and managed by breaking down the scope into manageable segments is called: Path of Construction. - Answers The optimal construction sequence to assemble the facility is called the __________________, and should be defined during the early planning stages of a project: Plant performance. - Answers Which is NOT a potential result of AWP? False - Answers The Critical Path Method reveals the contiguous path of activities in a network having the shortest total duration and thus defining the minimum duration of the project A - Revise the schedules logic B - Use overtime D - Use substitute materials or equipment E - Increase crew size - Answers What are some ways to accelerate a schedule (check all that apply)? Request for information - Answers What does RFI stand for? True - Answers Cost data provided by national firms (such as R.S.Means) must be adjusted to the specific project location. False - Answers Quality construction is good, and every designer should specify the highest-quality project components. Increased availability of labor - Answers Which of the following will NOT increase the

Meer zien Lees minder
Instelling
CNST 1361
Vak
CNST 1361

Voorbeeld van de inhoud

CNST 1361 Final Exam Questions with Correct Answers Latest Update 2025/2026

Unit price estimate - Answers Which type of estimate is the most accurate?

Advanced Work Packaging - Answers What does AWP stand for?

Lower initial cost. - Answers Which of these is not a reported benefit of AWP by the industry?

Construction Work Area - Answers The portion of the plot plan that has been defined jointly by
Engineering and Construction that represents a logical physical envelope of work is called:

Installation Work Package. - Answers The portion of work that contains all the necessary
elements for a single construction crew to complete that portion of the work is called:

Construction Work Package. - Answers The logical subdivision of a CWA construction scope
into a defined geographic area and discipline is called:

Work Breakdown Structure. - Answers The framework that represents the way a project is
defined, planned and managed by breaking down the scope into manageable segments is called:

Path of Construction. - Answers The optimal construction sequence to assemble the facility is
called the __________________, and should be defined during the early planning stages of a
project:

Plant performance. - Answers Which is NOT a potential result of AWP?

False - Answers The Critical Path Method reveals the contiguous path of activities in a network
having the shortest total duration and thus defining the minimum duration of the project

A-

Revise the schedules logic

B-

Use overtime

D-

Use substitute materials or equipment

E-

Increase crew size - Answers What are some ways to accelerate a schedule (check all that
apply)?

Request for information - Answers What does RFI stand for?

True - Answers Cost data provided by national firms (such as R.S.Means) must be adjusted to

, the specific project location.

False - Answers Quality construction is good, and every designer should specify the highest-
quality project components.

Increased availability of labor - Answers Which of the following will NOT increase the cost of a
project?

As quality expenditures increase, the value of the increased quality to the owner increases at a
decreasing rate. - Answers When considering project quality, which of the following is true?

Physical project size - Answers Which of the following is NOT a reason for construction cost
variation among different geographic locations?

Activity interrelations are not considered - Answers The following is a limitation of a bar chart
schedule.

Activity - Answers In a network schedule, what is the fundamental unit of work?

Network - Answers Activity on arrow and activity on node are both examples of which method of
scheduling?

Establish the project's objective - Answers Which of the following is the first step in the planning
and scheduling process?

True - Answers A matrix schedule provides the readability of a bar chart schedule while
addressing project logic.

Duration - Answers An increase in indirect costs could be directly attributable to an increase in
what aspect of a project?

True - Answers When estimates and schedules are initially prepared, unlimited resources are
assumed.

True - Answers To create an accurate coas flow projection, estimate and schedule information
must be accurately integrated.

Forecasting - Answers Which is the term that best describs the "projected outcome" for a
project?

True - Answers One important function of the documentation stage is storing project
information for future estimates, schedules, and project plans.

True - Answers Job diaries are subjective accounts of what occurred during the course of the
construction workday.

True - Answers An RFI is a formal request for information necessary to help clarify construction

Geschreven voor

Instelling
CNST 1361
Vak
CNST 1361

Documentinformatie

Geüpload op
22 november 2025
Aantal pagina's
8
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$11.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
joshuawesonga22 Liberty University
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
107
Lid sinds
1 jaar
Aantal volgers
1
Documenten
14501
Laatst verkocht
1 week geleden
Tutor Wes

Hi there! I'm Tutor Wes, a dedicated tutor with a passion for sharing knowledge and helping others succeed academically. All my notes are carefully organized, detailed, and easy to understand. Whether you're preparing for exams, catching up on lectures, or looking for clear summaries, you'll find useful study materials here. Let’s succeed together!

3.5

11 beoordelingen

5
4
4
1
3
3
2
2
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen