Geschreven door studenten die geslaagd zijn Direct beschikbaar na je betaling Online lezen of als PDF Verkeerd document? Gratis ruilen 4,6 TrustPilot
logo-home
Tentamen (uitwerkingen)

PMA Practice Test EXAM QUESTIONS AND CORRECT ANSWERS WITH RATIONALES LATEST UPDATE JUST RELEASED THIS YEAR

Beoordeling
-
Verkocht
-
Pagina's
107
Cijfer
A+
Geüpload op
22-11-2025
Geschreven in
2025/2026

PMA Practice Test EXAM QUESTIONS AND CORRECT ANSWERS WITH RATIONALES LATEST UPDATE JUST RELEASED THIS YEAR

Instelling
PMA Practice
Vak
PMA Practice

Voorbeeld van de inhoud

Page 1 of 107



PMA Practice Test EXAM QUESTIONS AND
CORRECT ANSWERS WITH RATIONALES LATEST
UPDATE JUST RELEASED THIS YEAR

Question: Which of the following estimating approaches would you use early in a project?




A. Analogous




B. Parametric




C. Bottom-up




D. Three-point - CORRECT ANSWER✔✔A.


Planning - Cost Management


Of the estimating approaches listed, only analogous is used early in a project, when little
information is known about the project. It is the quickest way of coming up with a total project
estimate but it is also the least accurate.


Question: The process of Identify Risk will result in which of the following?




A. Risk Management Plan

, Page 2 of 107




B. Risk Register




C. Risk Breakdown Structure




D. Risk versus Reward - CORRECT ANSWER✔✔B.


Planning - Risk Management


The process of Identify Risk will result in the creation of the Risk Register, which is the document
that will list all possible threats and opportunities that could occur during the project. The risk
management plan is an outcome of plan risk management and it will possibly include the risk
breakdown structure.


Question: As the project manager you have decided to separate the sources of risk by phase
and by the WBS. Using this technique you will find the riskiest areas of the project. Which of the
following best describes the technique employed?




A. Proper risk planning




B. Risk urgency assessment




C. Risk data quality assessment

, Page 3 of 107




D. Risk categorization - CORRECT ANSWER✔✔D.


Planning - Risk Management


While answer A may be correct it is too general. Answer B is a technique used to identify those
risks that could occur sooner in the project. Answer C is a technique used to ensure the quality
of the data used to identify and analyze risk. Risk categorization is a technique used to classify
risk and can be done through various methods, such as a sample list of risk categories, or it
could be done by phase, by the WBS, or by a formal risk breakdown structure.


Question: Your project team has just completed a quantitative analysis of project risk. They
have identified a 45% chance of a flood that would cost the project $50,000 in damages and
cleanup. They have also identified a 30% chance that the new piece of equipment recently
purchased by your organization will save the project $10,000. What is the expected monetary
value of these two risks? (Probability)x(impact)




A. $40,000




B. ($40,000)




C. $19,500




D. ($19,500) - CORRECT ANSWER✔✔D.


Planning - Risk Management

, Page 4 of 107


When calculating the contingency budget for a project, one popular method is called EMV or
expected monetary value. To calculate EMV for each of these risks you would multiply the
probability of occurrence and the impact of that occurrence. So, .45*$50,000= -$22,500. Then
you will notice that the second risk is an opportunity. To calculate the EMV for this opportunity
it would be, .30*$10,000= $3,000. These two figures would then be added together. So, a
negative $22,500 plus $3000 would equal -$19,500. A common way of showing negative
numbers is in parentheses.


Question: Two team members are having trouble getting along. They have attempted to resolve
their differences between themselves with no lasting outcome. As project manager you have a
discussion with them to identify the root cause. After much discussion, you decide that the best
way to take care of the situation is to have both team members go play a round of golf, which
they both enjoy. What conflict resolution technique have you employed?




A. Compromise/Reconcile




B. Force/Direct




C. Smooth/Accommodate




D. Collaborate/Problem Solve - CORRECT ANSWER✔✔C.


Executing - Human Resources Management


In this situation the project manager is using smoothing or accommodating, which means they
are deemphasizing the areas of disagreement and emphasizing the areas of agreement or
commonality. Compromising is when both parties give something up to reach an agreement.
Forcing or directing is when one party forces their desire or wish upon someone else.
Collaborating or problem-solving is when the conflict is treated as a problem, and possible

Geschreven voor

Instelling
PMA Practice
Vak
PMA Practice

Documentinformatie

Geüpload op
22 november 2025
Aantal pagina's
107
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$13.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
ressyshii Chamberlain College Of Nursing
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
61
Lid sinds
2 jaar
Aantal volgers
7
Documenten
2093
Laatst verkocht
2 weken geleden

3.7

9 beoordelingen

5
5
4
0
3
1
2
2
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen