During System Restoration, what is the optimal Frequency Range? - ANS 59.75 - 61 Hz
The 500 kV system has normal bus voltages between? - ANS 500 to 550 kV
When Connecting 2 islands, the operator must match? - ANS Voltage, Phase Angle and
Frequency
What are the Minimum Source Requirements for a 500kV line? (Gen/mile and load/mile) -
ANS 30 MW Gen/mile of energized 500 kV and 20 MW Load/mile of energized 500 kV
When will PJM issue a Minimum Generation Alert? (how many MW under normal operating
limits) - ANS When expected generation levels fall within 2500 MW of normal operating
limits
When a thunderstorm is nearing the BES should auto-reclosing be turned on? - ANS Yes
What does SCADA stand for? - ANS Supervisory Control & Data Acquisition
1 @COPYRIGHT 2025/2026 ALLRIGHTS RESERVED.
,What does IROL stand for? - ANS Interconnection Reliability Operating Limit
What does eDART stand for? - ANS Dispatcher Application and Reporting Tool
What is eDART used for? (Electronic Disp Reporting Tool) - ANS It is used for: Generation
Outage Scheduling, Instantaneous Reserve Checks, Generator Reactive Capabilities and to enter
and submit switching
What direction do VARS flow? - ANS From HIGH Voltage to LOW Voltage
What direction do MW flow? - ANS From HIGH Phase Angle to LOW Phase Angle
Which of the following factors are NOT used in forecasting load?
1) Weather Forecast
2) Historical Load Forecast
3) Historical Weather Data
4) Locational Marginal Pricing (LMP) Data - ANS 4
What one-way communication system is used to disseminate info to local call centers? -
ANS All-Call
The 3 categories of messages issued by PJM All-Call all EXCEPT:
1) Operational
2 @COPYRIGHT 2025/2026 ALLRIGHTS RESERVED.
,2) Informational
3) Conflicting Interchange Values
4) Emergency Procedures - ANS 3
When should, transmission outages should be submitted to PJM to avoid cancellation and to be
considered "on time?' - ANS First day of Month Prior to the Outage
What report will be requested by PJM when a Max Generation Alert is issued? -
ANS Supplementary Status Report (SSR)
The loss of a large generation unit on the PJM system can be detected by monitoring: -
ANS Frequency and PJM Area Control Error (ACE)
The PJM system is operated such that the contingency flow is less than the: - ANS Emergency
Rating
When ordered a 5% voltage reduction should be taken on: - ANS The Distribution System
TOs are required to report "Hot Line Work" on what voltage levels? - ANS 345 kV and Above
Load dump rating of an EHV line is determined by? - ANS 115% of the facility's 4 hour
Emergency Rating
During System Restoration, will closing additional tie lines increase the strength & stability of an
interconnected area? - ANS Yes
Which of the following factors influence load forecast (3)?
3 @COPYRIGHT 2025/2026 ALLRIGHTS RESERVED.
, 1) Weather
2) Temperature
3) Reactive Reserves
4) Day of the week - ANS 1, 2, 4
During system restoration, what is the voltage range the system should be kept between? -
ANS 90% and 105% maintain voltage profile between for system restoration
PJM will coordinate and direct all restoration lines of what voltage levels? - ANS 500kV and
above
How much load would you dump to increase the frequency by 1 Hz (percentage range)? -
ANS 6-10%
Generation is disconnected after 5 seconds, when the frequency: - ANS Drops below 57.5Hz
How much of the total Dynamic Reserve should be used on Under Frequency relay load? -
ANS
During System Restoration, capacitor banks should be kept off until how much of the load is
restored? - ANS 40%
Would PJM assume Frequency Control when the control of an interconnected area is too
burdensome for any Local Control Center? - ANS Yes
4 @COPYRIGHT 2025/2026 ALLRIGHTS RESERVED.
QUESTIONS WITH 100% CORRECT
ANSWERS LATEST VERSION 2025/2026.
During System Restoration, what is the optimal Frequency Range? - ANS 59.75 - 61 Hz
The 500 kV system has normal bus voltages between? - ANS 500 to 550 kV
When Connecting 2 islands, the operator must match? - ANS Voltage, Phase Angle and
Frequency
What are the Minimum Source Requirements for a 500kV line? (Gen/mile and load/mile) -
ANS 30 MW Gen/mile of energized 500 kV and 20 MW Load/mile of energized 500 kV
When will PJM issue a Minimum Generation Alert? (how many MW under normal operating
limits) - ANS When expected generation levels fall within 2500 MW of normal operating
limits
When a thunderstorm is nearing the BES should auto-reclosing be turned on? - ANS Yes
What does SCADA stand for? - ANS Supervisory Control & Data Acquisition
1 @COPYRIGHT 2025/2026 ALLRIGHTS RESERVED.
,What does IROL stand for? - ANS Interconnection Reliability Operating Limit
What does eDART stand for? - ANS Dispatcher Application and Reporting Tool
What is eDART used for? (Electronic Disp Reporting Tool) - ANS It is used for: Generation
Outage Scheduling, Instantaneous Reserve Checks, Generator Reactive Capabilities and to enter
and submit switching
What direction do VARS flow? - ANS From HIGH Voltage to LOW Voltage
What direction do MW flow? - ANS From HIGH Phase Angle to LOW Phase Angle
Which of the following factors are NOT used in forecasting load?
1) Weather Forecast
2) Historical Load Forecast
3) Historical Weather Data
4) Locational Marginal Pricing (LMP) Data - ANS 4
What one-way communication system is used to disseminate info to local call centers? -
ANS All-Call
The 3 categories of messages issued by PJM All-Call all EXCEPT:
1) Operational
2 @COPYRIGHT 2025/2026 ALLRIGHTS RESERVED.
,2) Informational
3) Conflicting Interchange Values
4) Emergency Procedures - ANS 3
When should, transmission outages should be submitted to PJM to avoid cancellation and to be
considered "on time?' - ANS First day of Month Prior to the Outage
What report will be requested by PJM when a Max Generation Alert is issued? -
ANS Supplementary Status Report (SSR)
The loss of a large generation unit on the PJM system can be detected by monitoring: -
ANS Frequency and PJM Area Control Error (ACE)
The PJM system is operated such that the contingency flow is less than the: - ANS Emergency
Rating
When ordered a 5% voltage reduction should be taken on: - ANS The Distribution System
TOs are required to report "Hot Line Work" on what voltage levels? - ANS 345 kV and Above
Load dump rating of an EHV line is determined by? - ANS 115% of the facility's 4 hour
Emergency Rating
During System Restoration, will closing additional tie lines increase the strength & stability of an
interconnected area? - ANS Yes
Which of the following factors influence load forecast (3)?
3 @COPYRIGHT 2025/2026 ALLRIGHTS RESERVED.
, 1) Weather
2) Temperature
3) Reactive Reserves
4) Day of the week - ANS 1, 2, 4
During system restoration, what is the voltage range the system should be kept between? -
ANS 90% and 105% maintain voltage profile between for system restoration
PJM will coordinate and direct all restoration lines of what voltage levels? - ANS 500kV and
above
How much load would you dump to increase the frequency by 1 Hz (percentage range)? -
ANS 6-10%
Generation is disconnected after 5 seconds, when the frequency: - ANS Drops below 57.5Hz
How much of the total Dynamic Reserve should be used on Under Frequency relay load? -
ANS
During System Restoration, capacitor banks should be kept off until how much of the load is
restored? - ANS 40%
Would PJM assume Frequency Control when the control of an interconnected area is too
burdensome for any Local Control Center? - ANS Yes