Questions with 100% Correct Answers |
Latest Update
What are the five phases of commissioning? - 🧠ANSWER ✔✔1.) Pre-
Design
2.) Design
3.) Construction
4.) Acceptance
5.) Post-Acceptance
,Studies indicate _ to _% savings in building operating costs when
comparing a comissioned building to a non-commissioned building. -
🧠ANSWER ✔✔8 to 20%
What is commissioning? - 🧠ANSWER ✔✔A process of documentation,
adjustment, testing, verification, and training performed specifically to
ensure that the finished facility operates in accordance with the owner's
documented project requirements and the construction documents.
Commissioning serves the owner's best interests by delivering a facility
with systems that perform as specified, intended, and paid for.
What does DID mean and provide a brief definition? - 🧠ANSWER
✔✔Design Intent Document - Details functional requirements and Owner's
expectations of how a building will be used and operated - Owner's Project
Requirements
What does BOD mean and provide a brief definition? - 🧠ANSWER
✔✔Basis of Design - The concepts, calculations, decisions, and product
selections used to meet the Owner's Project Requirements.
Designer's (A/E) services typically (do or do not) include field verification
that their design works as intended. - 🧠ANSWER ✔✔Do NOT
, Construction Manager's services typically (do or do not) include functional
verification that the installed systems meet design intent. - 🧠ANSWER
✔✔Do NOT
The CxA has a distinct responsibility to who? - 🧠ANSWER ✔✔The Owner
The CxA is not just another layer of inspection, but a catalyst for? -
🧠ANSWER ✔✔Communication that makes quality solutions possible.
The CxA (is or is not) an inspector. - 🧠ANSWER ✔✔Is NOT
The commissioning process provides verification that the ____ ____ ____
are implemented in both the ____ and ____. - 🧠ANSWER ✔✔Owner's
Project Requirements; Design and Construction
New construction commissioning costs _ to _% of total construction cost. -
🧠ANSWER ✔✔0.5 to 1.5%
Retrocommissioning costs _ to _% of total operation cost. - 🧠ANSWER
✔✔3 to 5%
New construction commissioning costs _ to _% of total mechanical system
construction cost. - 🧠ANSWER ✔✔2 to 3%