100% Correct
Which of the following is not a way in which a workcenter can be
organized?
a. According to function in a workcenter configuration
b. According to function in an assembly line
c. By product in assembly line
d. As a group technology cell (GT cell)
e. By product in a flow operation - 🧠 ANSWER ✔✔b. According to function
in an assembly line
, When work is scheduled in detail using the setup and run time required for
each order, it is called which of the following?
a. Infinite loading
b. Finite loading
c. Machine-limited
d. Labor-limited
e. Johnson's rule - 🧠 ANSWER ✔✔b. Finite loading
A material requirements planning system is an example of which of the
following scheduling systems?
a. Infinite loading, backward scheduling
b. Finite loading, backward scheduling
c. Infinite loading, forward scheduling
d. Finite loading, forward scheduling
e. None of these choices are correct - 🧠 ANSWER ✔✔a. Infinite loading,
backward scheduling