1. The job of the project manager is to:
A. Control all costs
B. Control costs, schedule, and performance of the project
C. Keep within the budget, no matter what
D. All of the above - 🧠 ANSWER ✔✔B. Control costs, schedule, and
performance of the project
2. The purpose of performing a forward pass is to:
A. Identify the critical path
, B. Determine the early start and the early finish times
C. Determine the late start and the late finish times
D. Determine the slack available in the process - 🧠 ANSWER ✔✔B.
Determine the early start and the early finish times
4. Multiple critical paths can exist under the critical path method (CPM)
because:
A. There is more than one way to complete the project
B. Different network paths can have the same total time
C. Great flexibility of activity sequences is available
D. None of the above - 🧠 ANSWER ✔✔B. Different network paths can have
the same total time
5. Project management requires:
A. Scheduling, planning, and controlling
B. Quantitative skills
C. Behavioral skills