ICC U2 UST Decommissioning Exam Questions 2025/2026 | Actual Questions and Answers Verified 100% Correct A permit to operate a UST system must have all of the following listed on the permit, EXCEPT: a.) The state UST identification number(s) b.) Name of the tank manufacturer and tank capacity c.) Permit expiration date d.) Monitoring requirements - ANSWER -b.) Name of the tank manufacturer and tank capacity CCR Title 23, Sec 2712(c) All underground pressurized product piping shall have an automatic line leak detector capable of detecting a 3-gallon per hour leak rate installed by______________. a.) July 1, 2003 b.) November 9, 2004 c.) July 1, 2004 d.) July 1, 1987 - ANSWER -b.) November 9, 2004 CCR Title 23, Sec 2636(f)(3) A temporary closure is appropriate for which of the following: a.) The UST system is empty and will be removed from service indefinitely b.) The UST system has ceased to store hazardous materials but will be used within the next 12 consecutive months c.) The UST system is unable to meet compliance requirements and will be removed d.) The UST system has been red-tagged - ANSWER -b.) The UST system has ceased to store hazardous materials but will be used within the next 12 consecutive months CCR Title 23, Sec 2671 & 2670 A local agency determines that a UST facility within the last year had compliance issues. Prior to issuing a new permit or renewal to operate an UST the local agency shall: a.) Ask the state to assist in a joint inspection b.) Request the owner/operator to submit a "Return to Compliance" form. c.) Refer to a District Attorney Investigator d.) Inspect the facility and determine compliance - ANSWER -d.) Inspect the facility and determine compliance CCR Title 23, Sec 2712(c) Spill containers must be tested no less than _______________ to demonstrate that it is capable of containing the hazardous substances until it is detected and cleaned up. a.) Every 6 months b.) Every 36 months c.) Every 12 months d.) At the time of install or replacement - ANSWER -c.) Every 12 months H&SC, Sec 25284.2 All the following components require third party certification, except: a.) Automatic tank gauging systems b.) Statistical inventory reconciliation methods c.) Spill Containment lids d.) Liquid phase out-of-tank products - ANSWER -c.) Spill Containment lids The exterior surface of an underground storage tank must bear a marking or label which shows the following information, except: a.) Design pressure in psig b.) Useable capacity in gallons. c.) Width of the interstitial space d.) Identity of manufacturer - ANSWER -c.) Width of the interstitial space CCR Title 23, Sec 2631(b) Which of the following is not a confined space: a.) A really deep turbine sump b.) A space not designed for continuous employee occupancy c.) An area with limited access d.) An area with limited ventilation - ANSWER -d.) An area with limited ventilation CCR Title 8, Sec 5157(b) Records for UST construction, repairs, lining, and upgrades must be kept for: a.) 3 years b.) 10 years c.) 5 years d.) The life of the tank - ANSWER -d.) The life of the tank CCR Title 23, Sec 2712(b) Under-dispenser containment was required at the time of installation for all UST systems installed after _________________.

Meer zien Lees minder
Instelling
ICC U2 UST Decommissioning
Vak
ICC U2 UST Decommissioning

Voorbeeld van de inhoud

ICC U2 UST Decommissioning Exam Questions
2025/2026 | Actual Questions and
Answers Verified 100% Correct

A permit to operate a UST system must have all of the following listed on the
permit, EXCEPT:

a.) The state UST identification number(s)
b.) Name of the tank manufacturer and tank capacity
c.) Permit expiration date
d.) Monitoring requirements - ANSWER -b.) Name of the tank manufacturer and
tank capacity

CCR Title 23, Sec 2712(c)

All underground pressurized product piping shall have an automatic line leak
detector capable of detecting a 3-gallon per hour leak rate installed
by______________.

a.) July 1, 2003
b.) November 9, 2004
c.) July 1, 2004
d.) July 1, 1987 - ANSWER -b.) November 9, 2004

CCR Title 23, Sec 2636(f)(3)

A temporary closure is appropriate for which of the following:

a.) The UST system is empty and will be removed from service indefinitely
b.) The UST system has ceased to store hazardous materials but will be used within
the next 12 consecutive months

,c.) The UST system is unable to meet compliance requirements and will be
removed
d.) The UST system has been red-tagged - ANSWER -b.) The UST system has
ceased to store hazardous materials but will be used within the next 12 consecutive
months

CCR Title 23, Sec 2671 & 2670

A local agency determines that a UST facility within the last year had compliance
issues. Prior to issuing a new permit or renewal to operate an UST the local agency
shall:

a.) Ask the state to assist in a joint inspection
b.) Request the owner/operator to submit a "Return to Compliance" form.
c.) Refer to a District Attorney Investigator
d.) Inspect the facility and determine compliance - ANSWER -d.) Inspect the
facility and determine compliance

CCR Title 23, Sec 2712(c)

Spill containers must be tested no less than _______________ to demonstrate that
it is capable of containing the hazardous substances until it is detected and cleaned
up.

a.) Every 6 months
b.) Every 36 months
c.) Every 12 months
d.) At the time of install or replacement - ANSWER -c.) Every 12 months

H&SC, Sec 25284.2

All the following components require third party certification, except:

a.) Automatic tank gauging systems
b.) Statistical inventory reconciliation methods

,c.) Spill Containment lids
d.) Liquid phase out-of-tank products - ANSWER -c.) Spill Containment lids

The exterior surface of an underground storage tank must bear a marking or label
which shows the following information, except:

a.) Design pressure in psig
b.) Useable capacity in gallons.
c.) Width of the interstitial space
d.) Identity of manufacturer - ANSWER -c.) Width of the interstitial space

CCR Title 23, Sec 2631(b)

Which of the following is not a confined space:

a.) A really deep turbine sump
b.) A space not designed for continuous employee occupancy
c.) An area with limited access
d.) An area with limited ventilation - ANSWER -d.) An area with limited
ventilation

CCR Title 8, Sec 5157(b)

Records for UST construction, repairs, lining, and upgrades must be kept for:

a.) 3 years
b.) 10 years
c.) 5 years
d.) The life of the tank - ANSWER -d.) The life of the tank

CCR Title 23, Sec 2712(b)

Under-dispenser containment was required at the time of installation for all UST
systems installed after _________________.

, a.) July 1, 1987
b.) January 1, 2000
c.) January 1, 1984
d.) December 31, 2003 - ANSWER -b.) January 1, 2000

CCR Title 23, Sec 2636(g)(1)(A)

Cathodic protection systems must be inspected by a certified cathodic protection
tester within __________________months of installation:

a.) 3
b.) 6
c.) 12
d.) 18 - ANSWER -b.) 6

CCR Title 23, Sec 2635(a)(2)(A)

A secondary containment system which is not an integral part of primary
containment shall be designed and constructed according to an engineering
specification approved by a third party. The secondary containment system shall
contain ______________ of the volume of the largest primary container within it,
in the case of multiple primary containers:

a.) 100 percent
b.) 10 percent
c.) 110 percent
d.) 150 percent - ANSWER -d.) 150 percent

CCR Title 23, Sec 2631(e)(1)(B)

All the following are approved overfill prevention systems, except:

a.) Automatic shutoff devices
b.) Spill Containers
c.) Overfill alarms

Geschreven voor

Instelling
ICC U2 UST Decommissioning
Vak
ICC U2 UST Decommissioning

Documentinformatie

Geüpload op
2 december 2025
Aantal pagina's
73
Geschreven in
2025/2026
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

$18.49
Krijg toegang tot het volledige document:

Verkeerd document? Gratis ruilen Binnen 14 dagen na aankoop en voor het downloaden kun je een ander document kiezen. Je kunt het bedrag gewoon opnieuw besteden.
Geschreven door studenten die geslaagd zijn
Direct beschikbaar na je betaling
Online lezen of als PDF

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
TopGradeGuru Teachme2-tutor
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
15
Lid sinds
1 jaar
Aantal volgers
0
Documenten
2398
Laatst verkocht
1 maand geleden
GRADEHUB

We provide access to a wide range of professionally curated exams for students and educators. It offers high-quality, up-to-date assessment materials tailored to various subjects and academic levels. With instant downloads and affordable pricing, it\'s the go-to resource for exam preparation and academic success.

1.5

2 beoordelingen

5
0
4
0
3
0
2
1
1
1

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Bezig met je bronvermelding?

Maak nauwkeurige citaten in APA, MLA en Harvard met onze gratis bronnengenerator.

Bezig met je bronvermelding?

Veelgestelde vragen