Corrosion Specialist - correct answers ✅designs and certifies cathodic
protection system
Secondary containment shall be constructed to contain at least the following
volumes: - correct answers ✅A. 100% of usable capacity of primary where
there is only one primary is within the secondary
B. 150% of the largest container if there are multiple primary containers in a
single secondary
Cathodic protection tester will test cathodic protection system within __
months of installation and every __ years thereafter - correct answers ✅6
months
3 years
Spill container shall meet the following requirements: - correct answers
✅A. If made of metal, exterior wall shall be protected from galvanic
corrosion
B. Shall have minimum capacity of 5 gallons (19 L)
, ICC / UST Exam Questions and Answers (Latest Update
2023) Solved Questions
C. Shall have drain valve which allows drainage of the collected spill into the
primary container or provide means to keep spill cont empty
Overfill prevention shall alert transfer operator when tank is __% full -
correct answers ✅90%
Flapper Valves shall provide positive shut off when tank is filled to no more
than __% capacity - correct answers ✅95%
Primary pressurized piping shall be tested for tightness hydrostatically at
__% of design operating pressure - correct answers ✅150%
Date that all UST systems must have Line Leak Detector installed - correct
answers ✅November 9,2004
Secondary containment testing shall be done upon ____, __months, and
every ___ months or ____ years thereafter - correct answers ✅Installation
6 months
36 months or 3 years