At what intervals should equipment be inspected -
....ANSWER...Every day do circle check, start of every
shift. Every 30 days for rigging. 90 days for full inspection
How many cable clips are required on a cable and how are
they installed - ....ANSWER...Minimum of 3, u bolt on the
dead, saddle on the live
What is the purpose of a thimble - ....ANSWER...to keep
the loop in the eye from crushing
Can internal combustion engines be operated in a confined
space - ....ANSWER...Yes if properly ventalated
,Who is allowed on a lift truck other than operator -
....ANSWER...No one
What restricts the lifting capacity of hoisting equipment -
....ANSWER...Pressure relief valve
What is the average hydraulic pressure of a lul -
....ANSWER...1,800 lbs psi to 2,400 lbs psi
What is the total force exerted on a 4" cylinder at 1,800 psi
- ....ANSWER...4x3.14=12.56 x 1,800 = 22,608 lbs of
force
Where should the approved hand signals be posted -
....ANSWER...On the machine
What is the weakest part of a hydraulic system -
....ANSWER...Hoses
What causes starving of hydraulic system -
....ANSWER...Low fluid, dirty filter, leaks, linked hoses
,Who has the right of way when operating equipment -
....ANSWER...Pedestrian
Lost some reasons why you would replace a hose -
....ANSWER...Broken, cracked, chafed, bulging or leaking
What is considered superimposed weight around a trench
or work area - ....ANSWER...Any weight that is not
normally there, vehicles, spoil
If you cannot see where the work is being done, do not
move unless you have what? - ....ANSWER...A signal
person who has a clear view of the operation directing you
What is a tag line - ....ANSWER...A line used to control
the loads being handled by hoisting equipment
When can you carry a load over someone -
....ANSWER...Never
, What are the purpose of mats, steel plates and timber pads
- ....ANSWER...Distribution of weight
Who is responsible for safe operation of the machine -
....ANSWER...The operator
What should you look for before starting work -
....ANSWER...Soft soil, wet areas, power lines, wells, dig
safe marks for other utilities
What should you do with open trenches or holes at the end
of the day - ....ANSWER...Cover or backfill unless you
have fencing
What should you do when working on a public way -
....ANSWER...Make area safe for public with cones, signs,
caution tape, saftey vests, and arrow board
What should you do with equipment when finished for the
day - ....ANSWER...Park on firm level surface, chalk
wheels, secure equipment, take the keys. Shut off master
disconnect