AND ANSWERS VERIFIED 100% CORRECT
In situations where an initial exemption was applicable because LDAs were
related to emergency work, VSMP authority shall be advised of the disturbance
within - ANSWER -7 days of commencing the LDA and shall submit a permit
application within 30 days of starting the land-disturbing activity
Localities with MS4 - ANSWER -must adopt and administer a stormwater
program
Localities without MS4 - ANSWER -may choose to administer a VSMP or have
DEQ administer the program
DEQ is responsible for enforcing the ____ while locality ____ are responsible for
enforcing local ordinances - ANSWER -Construction GP, VSMP
A locality VSMP authority must include enforcement authority and a schedule of
civil penalties for enforcement actions in its local ordinance. The maximum
penalty the authority may issue is - ANSWER -$32,500 per violation per day
Any civil penalty assessed by a court as a result of a summons issued by a locality
VSMP authority must be paid - ANSWER -into the locality's treasury
Any person who violates..... shall be subject to a civil penalty not to exceed -
ANSWER -$32, 500
Chesapeake Bay Preservation Areas that result in a land disturbance greater than
or equal to ____ and less than ____ - ANSWER -2,500 ft^2, 1 acre
CBPA LDAs must have - ANSWER -approved E&SC plan, approved SWM plan,
local approval to start land disturbance, long-term maintenance agreement,
construction record drawings
, CBPA LDAs do not require - ANSWER -Construction GP, Pollution prevention
Plan, Additional control measures to address TMDL
State entities and linear projects ___ submit a single set of standards and
specifications to DEQ for approval, federal entities ____ - ANSWER -must, may
Name the 5 steps in order of the permitting process - ANSWER -submittal of ESC
plans and SWM plans, SWM plan review and approval, registration statement
entry into Construction GP, Construction GP approved by DEQ, Locality VSMP
authority approval to start land disturbance
The locality VSMP authority has ___ days to determine the completeness of a
stormwater management plan and to notify the applicant of its determination -
ANSWER -15
If the plan is complete and the applicant has been notified within 15 days of
submission, the locality VSMP authority (plan reviewer) has ___ days from the
time of notification to review the plan - ANSWER -60
Operators of a single-family detached residential structures that disturb equal to or
greater than one acre of land are - ANSWER -not required to submit a registration
statement
VSMP authority must keep project records, including approved SWM plans and
registration statements, for ___ years after state permit termination or project
completion - ANSWER -3 years
VSMP authority must keep post construction stormwater management facility
inspection records for __ years from the date of inspection - ANSWER -5
DEQ is required to conduct a program review once every - ANSWER -5 years
A locality VSMP must be at least as stringent as what state permit? - ANSWER -
Construction GP