Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Exam (elaborations)

GMS450 FINAL EXAM QUESTIONS AND ANSWERS

Rating
-
Sold
-
Pages
29
Grade
A+
Uploaded on
11-12-2025
Written in
2025/2026

GMS450 FINAL EXAM QUESTIONS AND ANSWERS Project Crashing - CORRECT ANSWERShortening some activities within a project to reduce overall project completion time.

Institution
GMS450
Course
GMS450

Content preview

GMS450 FINAL EXAM QUESTIONS AND ANSWERS
Project Crashing - CORRECT ANSWER✅✅Shortening some activities within a project to reduce overall
project completion time.



Normal Time - CORRECT ANSWER✅✅The time necessary to complete an activity under normal
conditions.



Normal Cost - CORRECT ANSWER✅✅The activity cost associated with the normal time.



Crash Time - CORRECT ANSWER✅✅The shortest possible time to complete an activity.



Crash Cost - CORRECT ANSWER✅✅The activity cost associated with the crash time.



Cost to Crash/Period - CORRECT ANSWER✅✅=(CC-NC)/(NT-CT)



Which Activities Should Be Crashed? - CORRECT ANSWER✅✅One or more of the activities in the critical
path should be chosen to crash. The activity with the lowest cost to the firm should be crashed.



Resource Leveling - CORRECT ANSWER✅✅- When the project is large and contains many resource over-
allocations, resource leveling must be accomplished.

- It is a technique in which start and finish dates are adjusted based on resource constraints w/ the goal
of balancing demand for resources w/ the available supply.

- Purpose: to create a smoother distribution of resource usage.

- Aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack
allowances.

- Done by delaying or splitting tasks until the resources assigned to them are no longer over-distributed.



Activity Slack - CORRECT ANSWER✅✅Formula: S = LF - EF or LS - ES



Pseudoactivities - CORRECT ANSWER✅✅- Several projects can be linked together w/ pseudoactivities.

,- They have duration, but require no resources.

- They allow a set of projects to be linked and dealt w/ as though it were a single project.

- Individual projects are interrelated by specifying predecessor/successor relationships.



Criteria of Priority Rules - CORRECT ANSWER✅✅1. Schedule slippage: the amount project or set of
projects delayed by the application of a leveling rule. The PM must trade off penalty costs or displeasure
of clients against the cost of adding resources.

2. Resource utilization: the extent to which resources are over or under worked.

3. In-process inventory: amount of unfinished work in the system.

* The min. slack rule is the best overall priority rule according to research, giving the best combo. of
minimum project slippage, minimum resource idle-time and minimum in-process inventory.



Problems w/ Traditional Project Management - CORRECT ANSWER✅✅- Additional safety time should
be implemented beyond the work content time required to be embedded within the task duration to
increase the probability and high-confidence that the task will be completed on time.

Problems include:

- Not starting task until the last moment

- Delaying completion of task



Goldratt's Critical Chain - CORRECT ANSWER✅✅- Eli Goldratt created critical chain project mgmt. in
response to many projects being dogged by performance manifested in:

1) Longer than expected duration

2) Frequently missed deadlines

3) Increased costs in excess of budget

4) Substantially less deliverables than originally promised



Multitasking - CORRECT ANSWER✅✅- Assigning team members to multiple projects and having them
allocate their time across these projects.

- Typically a penalty or cost associated w/ switching from working on one project to another (usually
extends activity times)

, Goldratt's Solution - CORRECT ANSWER✅✅- Suggests that the key to resolving this is to schedule the
start of new projects based on the availability of bottleneck resources

- Suggests time buffers between bottleneck resource and resources that feed it.

* A bottleneck (or constraint) in a supply chain means the resource that requires the longest time in
operations of the supply chain for certain demand.



Two Potential Sources That Can Delay the Project - CORRECT ANSWER✅✅1) Delay in the tasks that
make up the critical chain.

2) Delay in activity feeding the critical chain that results in delay of the critical chain.



Project Buffer - CORRECT ANSWER✅✅- A project buffer is inserted at the end of the project network
between the last task and the completion date

- Any delays on the longest chain of dependent tasks will consume some of the buffer but will leave the
completion date unchanged and protect the project.



Feeding Buffer - CORRECT ANSWER✅✅- Delays on paths of tasks feeding into the longest chain can
impact the project by delaying a subsequent task on the critical chain.

- The feeding buffer is typically recommended to be half the size of the safety time taken out of the
feeding path.



Project Risk - CORRECT ANSWER✅✅- Definition: an uncertain event or condition that, if it occurs, has a
positive or negative effect on at least one project objective.

- Projects are all about uncertainty. Uncertainty cannot be eliminated, however, it can be minimized
with effective PM



Risk Management - CORRECT ANSWER✅✅- Process of identifying, analyzing and responding to project
risk in order to maximize positive outcomes.



Risk Mgmt. Breakdown Into Sub-Processes - CORRECT ANSWER✅✅1. Risk management planning

2. Risk identification

3. Qualitative risk analysis

4. Quantitative risk analysis

Written for

Institution
GMS450
Course
GMS450

Document information

Uploaded on
December 11, 2025
Number of pages
29
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

$13.49
Get access to the full document:

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
STANGRADES Stanford University
Follow You need to be logged in order to follow users or courses
Sold
88
Member since
1 year
Number of followers
1
Documents
11997
Last sold
3 weeks ago
STAN-GRADES

EXCELLENCY IN ACADEMIC MATERIALS

3.4

14 reviews

5
6
4
1
3
3
2
1
1
3

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions